海底盾构隧道孤石爆破预处理关键技术
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
文章针对基于孤石形状、分布位置的随机性及其高强度,盾构机无法直接掘进通过这一工程难题,在前期物探及钻孔验证的基础上,对钻孔参数和爆破方案设计进行了分析;通过采用对临近隧洞爆破震动跟踪监测和爆破后炮孔取芯验证的方法,总结出了一套针对海底盾构区间孤石爆破预处理的施工方法。
In some cases, it is not practical for a shield machine to pass directly through certain materials because of geometry, randomness of location, and strength of boulders. Based on previous geophysical prospecting and drilling, an analysis of the drilling parameters and the blasting scheme was performed to establish a design. Based on blast vibration monitoring in an adjacent tunnel and blasthole coring, this paper summarizes the construction method of pretreatment for boulder blasting in a shield-driven tunnel under the sea, and offers some rationalized proposals.
引文
[1]王梦恕.21世纪是隧道及地下空间大发展的时代[J].岩土工程界,2000,3(6):3-15Wang Mengshu.21st Century-the Epoch for the Great Development of Tunnels and Underground Space[J].Geological Engineering World,2000,3(6):3-15
    [2]王梦恕.我国地下铁道施工方法综述与展望[J].地下空间,1998,18(2):98-103Wang Mengshu.A Summary and Advance of Construction Technologies for Metro in China[J].Underground Space,1998,18(2):98-103
    [3]张凤祥,朱合华,傅德明.盾构隧道[M].北京:人民交通出版社,2004Zhang Fengxiang,ZhuHehua,Fu Deming.Shield Tunnelling Method[M].Beijing:China Communications Press,2004
    [4]地盘工学会(日)著,牛清山,陈凤英,徐华(译).盾构法的调查、设计、施工[M].北京:中国建筑工业出版社,2008The Japanese Geotechnical Society.Investigation,Design and Construction of Shield Tunnelling[M].Beijing:China Architecture&Building Press,2008
    [5]竺维彬,鞠世健.复合地层中的盾构施工技术[M].北京:中国科学技术出版社,2006Zhu Weibin,Ju Shijian.Shield Tunnelling Technology in Mixed Face Ground Conditions[M].Beijing:ChineseScienceand Technology Press,2006
    [6]中华人民共和国行业标准.JTS204-2008水运工程爆破技术规范[S].北京:人民交通出版社,2008Industrial Standards of the People's Republic of China.JTS204-2008Technical Code of Blasting for Port and Waterway Engineering[S].Beijing:China Communications Press,2008
    [7]赵根.深水条件下围堰拆除爆破技术研究[D].安徽:中国科学技术大学,2008Zhao Gen.Study on Technology of the Cofferdam Demolition Blasting in Deep Water Condition[D].Anhui:University of Science and Technology of China,2008
    [8]陈墩科,苏利军,刘立新.三峡三期围堰深水硐室爆破药量计算方法探讨[J].爆破,2006,23(1):82-84Chen Dunke,Su Lijun,Liu Lixin.Research on Charge Calculation of Deep-Water Chamber Blasting in the3rd Stage Cofferdam of Three Gorges Project[J].Blasting,2006,23(1):82-84
    [9]陈晓强,周方毅,张可玉,等.水下爆破工程中炸药药量的修正计算[J].海洋工程,2004,22(1):107-110Chen Xiaoqiang,Zhou Fangyi,Zhang Keyu,et al.Modifying Calculation of the ExplosiveAmount in the Underwater Demolition[J].The Ocean Engi-neering,2004,22(1):107-110
    [10]刘美山,李丹,彭翠玲,等.大型水电站导流洞围堰拆除爆破关键问题分析[J].爆破,2006,23(2):80-84Liu Meishan,Li Dan,Peng Cuiling,et al.Analysis of Key Problems of Explosive Demolition for Cofferdam of Water Conveyance Tunnel on Large Hydropower Station[J].Blasting,2006,23(2):80-84
    [11]肖兴恒,曹芡.三峡工程二期围堰拆除施工难点及对策[J].中国三峡建设,2002,9(1):10-11Xiao Xingheng,CaoQian.Removal of Second-Phase Cofferdams at Three Gorges Project[J].China Three Gorges Construction,2002,9(1):10-11
    [12]余永强,路耀邦,杨小林,等.高地应力断裂破碎隧道爆破开挖震动效应[J].工程爆破,2010,16(3):48-51Yu Yongqiang,Lu Yaobang,Yang Xiaolin,et al.BlastingVibration Effect on Tunnel Excavation with High Geostress and Fracture Zones[J].Engi-neering Blasting,2010,16(3):48-51
    [13]中华人民共和国国家标准.GB6722-2003爆破安全规程[S].北京:中国标准出版社,2003National Standards of the People's Republic of China.GB6722-2003Safety Regulations for Blasting[S].Beijing:Standards Press of China,2003
    [14]汪旭光,于亚伦.关于爆破震动安全判据的几个问题[J].工程爆破,2001,7(2):88-91Wang Xuguang,YuYalun.On Several Problems of SafetyCriterion for Blasting Vibration[J].Engineering Blasting,2001,7(2):88-91
    [15]石崇,毕卫国.爆破地震破坏判据的探讨[J].岩土力学,2004,25(z1):115-118Shi Chong,Bi Weiguo.Discussionof Blasting Damage Criteria[J].Rock and Soil Mechanics,2004,25(Supp.1):115-118