西安地铁2号线隧道穿越地裂缝带的设防参数
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
基于西安地裂缝成因、基本特征和未来活动趋势分析,通过几何缩比为1:5的地裂缝活动模型试验和地裂缝活动对盾构隧道影响的数值模拟计算,研究了西安地铁2号线隧道正交穿越地裂缝带的设防参数。通过分析地裂缝年平均活动速率和历史最大活动量,确定了与地铁2号线相交的各条地裂缝的最大垂直位移量的预测值和设计建议值。模型试验和数值模拟结果表明,正交条件下地铁隧道在地裂缝活动地段的设防宽度为60m,即上盘为35m,下盘为25m;沿隧道纵向地裂缝两侧地层变形规律呈现台阶状突变变形,隧道纵向设计可将上盘视为整体下降来考虑;地铁隧道穿越地裂缝带必须分段设缝以适应地裂缝的变形,其分段长度在地裂缝主影响区按10m进行设防,在一般影响区可按10~15m进行分段设防。研究结果可为地铁隧道穿越地裂缝带的结构设计提供参考。
Based on analyzing the genesis,essential characteristics and tendencies of ground fissures in Xi’an,the physical model tests with a geometric proportion of 1:5 for active ground fissure and numerical simulation for the effect of active ground fissure on metro tunnel are carried out to study the design parameters of Xi’an metro line 2 tunnel orthogonally passing through the active ground fissure zones.On the basis of the average annual active rate of ground fissures and compared with the historical maximum displacements of ground fissures,the predicted and suggested maximum vertical displacements design values of each active ground fissure along the metro line 2 in the design life of 100 years are put forward.The test and simulation results show that the design width of metro tunnel orthogonally passing through the active ground fissure zone could be 60 m;i.e.35 m in the hanging wall and 25 m in the footwall of active ground fissure zone.The stratum deformation along the tunnel axis ground fissure appears stepped mutational deformation;and integral descent of the hanging wall of ground fissure could be adopted in the design of tunnel longitudinal structure.Metro tunnel passing through the active ground fissure zones should be segmented by deformation joints to adapt the deformation of active ground fissures;the design length of sectional tunnel in main influence zone is 10 m;and in the minor influence zone that is 10 to 15 m.The conclusions will provide for reference to the design of lining structure of metro tunnel passing through the active ground fissure zones.
引文
[1]张家明.西安地裂缝研究[M].西安:西北大学出版社,1990.
    [2]彭建兵.渭河盆地活动断裂与地质灾害[M].西安:西北大学出版社,1992.
    [3]李永善.西安地裂缝及渭河盆地活断层研究[M].北京:地震出版社,1992.
    [4]王景明.地裂缝及其灾害的理论与应用[M].西安:陕西科学技术出版社,2000.
    [5]陕西省建设厅.DBJ61-6-2006西安地裂缝场地勘察与工程设计规程[S].西安:陕西省建筑标准设计办公室发行,2006.
    [6]赵其华,王兰生.构造重力扩展机制的地质力学模型[J].工程地质学报,1995,2(3):21-27.ZHAO Qi-hua,WANG Lan-sheng.Study of geomechanical simulation of tectonic gravity spreading mechanism[J].Journal of Engineering Geology,1995,2(3):21-27.
    [7]易学发.西安市地面不均匀沉降及地裂缝成因的讨论[J].地震,1984,10(6):50-54.YI Xue-fa.A discussion on the ground subsidence and the genesis of ground fissure in Xi’an city[J].Earthquake,1984,10(6):50-54.
    [8]刘国昌.西安的地裂缝[J].西安地质学院学报,1986,10(4):9-22.LIU Guo-chang.Ground fissure of Xi’an[J].Journal of Xi’an Geology College,1986,10(4):9-22.
    [9]彭建兵,陈立伟,黄强兵,等.地裂缝破裂扩展的大型物理模拟试验研究[J].地球物理学报,2008,51(6):1826-1834.PENG Jian-bing,CHEN Li-wei,HUANG Qiang-bing,et al.Large-scale physical simulative experiment on ground-fissure expanison mechanism[J].Chinese Journal of Geophysics,2008,51(6):1826-1834.
    [10]王景明.渭河地震带地裂与地震活动的周期性[J].地震学报,1985,7(2):190-201.WNAG Jing-ming.Periodicity of ground fissures and earthquakes in the earthquake belt of the Weihe River[J].Acta Seismologica Sinica,1985,7(2):190-201.
    [11]晏同珍.西安地面沉降及地裂缝阶段预测[J].现代地质,1990,4(3):101-109.YAN Tong-zhen.Developing stage forecast of land subsidence and ground fissure Xi’an[J].Modern Geology,1990,4(3):101-109.
    [12]徐光黎,张家明,佟永贺,等.西安市地裂缝的时空预测预报[J].西北地震学报,1992,14(4):75-81.XU Guang-li,ZHANG Jia-ming,TONG Yong-he,et al.Space-time prognosis for ground fissures in Xi’an city[J].Northwest Seismological Journal,1992,14(4):75-81.
    [13]李新生,闫文中,李同录,等.西安地裂缝活动趋势分析[J].工程地质学报,2001,9(1):39-44.LI Xin-sheng,YAN Wen-zhong,LI Tong-lu,et al.Analysis on the movement tendency of Xi’an ground fissures[J].Journal of Engineering Geology,2001,9(1):39-44.
    [14]黄强兵,彭建兵,范文,等.西安地铁二号线沿线地裂缝未来位错量估算及工程分级[J].工程地质学报,2007,15(4):469-474.HUANG Qiang-bing,PENG Jian-bing,FAN Wen,et al.Estimation of the maximum displacement of ground fissures along Xi’an Metro Line2and its engineering classification[J].Journal of Engineering Geology,2007,15(4):469-474.
    [15]黄强兵,彭建兵,门玉明,等.地裂缝对地铁明挖整体式衬砌隧道影响机制的模型试验研究[J].岩石力学与工程学报,2008,27(11):2324-2331.HUANG Qiang-bing,PENG Jian-bing,MEN Yu-ming,et al.Model test study on effect of ground fissure on open-cut metro tunnel with integral lining[J].Chinese Journal of Rock Mechanics and Engineering,2008,27(11):2324-2331.
    [16]黄强兵,彭建兵,樊红卫,等.西安地裂缝对地铁隧道的危害及防治措施研究[J].岩土工程学报,2009,31(5):781-788.HUNAG Qiang-bing,PENG Jian-bing,FAN Hong-wei,et al.Metro tunnel hazards induced by active ground fissures in Xi’an and relevant control measures[J].Chinese Journal of Geotechnical Engineering,2009,31(5):781-788.