陕西省供电系统在汶川地震中的破坏及震害评估
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
受5.12汶川特大地震的影响,与四川省毗邻的陕西省供电设施受到不同程度的破坏。作为生命线工程的重要组成部分,电力系统的正常运行对震区人民群众的生产生活自救及灾后重建具有重要的意义。对陕西省内各供电系统的建构筑物及电力设备在主震发生后进行实地调查及评估,对建构筑物及电力设备的不同受损情况进行分类,对破坏形式及规律进行总结,并给出初步解决方案。
The electric power system in Shaanxi province had been distroied seriously after 5.12 Wenchuan M8.0 earthquake.As the component of lifeline system, the good work of electric power system was very important for the people's work and life after disaster in earthquake region.This paper introduces the investigaion results of buildings and electric equipments in power plants and substations influenced by earthquake in Shaanxi province,classifies the different destroy degree of buildings and equipments,summarizes the distroy rules of electric power system,and gives some advice in reconstruction.
引文
[1]GB/TB18203.3—2000地震现场工作第三部分:调查规范[S].北京:中国国家标准化管理委员会,2000.
    [2]GB/TB18208.4—2005地震现场工作第四部分:灾害直接损失评估[S].北京:中国国家标准化管理委员会,2005.
    [3]GB50011—2001建筑抗震设计规范[S].北京:中国建筑工业出版,2001.
    [4]GB50260—96电力设施抗震设计规范[S].北京:中国建筑工业出版社,1996.
    [5]陕西省电力公司建构筑物震害受损情况调查初步结论及费用估算汇报[R].西安:陕西省电力设计院,2008.
    [6]文波.隔震技术在变电建筑物中的应用研究[D].西安:西安理工大学,2004.