煤矿巷道涌水勘探与地面成孔注浆加固治理
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
针对某煤矿巷道二次出现涌水淹井事故,对矿区分别进行二维地震勘探和瞬变电磁法勘探,通过对勘探的结果进行综合分析,选定地面成孔注浆堵水的加固方案,最后介绍了地面注浆钻孔布设方案和注浆工艺,为类似工程提供了指导。
As for second flooded coal mine accident of tunnel shaft,two-dimensional seismic exploration and transient electromagnetic exploration in the mining area were performed through a comprehensive analysis for the results,the hole grouting reinforcement program on the ground was elected,and finally the ground grouting drilling and grouting technology were introduced,which provided the direction for the similar projects.
引文
[1]张先哲,尚照顺.某煤矿+60巷道地面成孔注浆堵水设计方案[R].河南豫中地质勘察工程公司,2005.
    [2]中华人民共和国国家标准,煤田钻探技术规程[S].
    [3]YSJ 211-92,YB J 44-92,注浆技术规程[S].
    [4]彭振斌.注浆工程设计计算与施工[M].武汉:中国地质大学出版社,1997.