航空型号生产项目集成进度控制方法
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
针对航空型号生产项目的特点,提出了一种综合项目工期、成本及质量等多目标的集成进度控制方法。该方法中,以集成进度控制模型为理论基础,采用M-BOM作为计划制定的基本数据源,结合WBS与分级网络计划技术产生多目标集成进度计划;运用EVM思想结合监控过程构建集成进度监控的具体方法。最后,使用自主开发的软件系统,分析了某型飞机生产项目的实例,验证了方法的有效性。
The method of integrating schedule control is proposed on aviation manufacturing projects.Analyzing the background of aviation manufacturing,the model of integrating schedule control is presented in which the indexes of the time,cost and quality are integrated into progress plan.On the basis of the model,regarding the product configuration information from M-BOM as the basic data,the WBS and multi-layer network scheduling and planning technique is utilized in establish progress plan.Then,according to the process of integrating schedule control,the status analysis method of project based on Earned Value Management(EVM) is discussed.Furthermore,simulation of the aviation assembly project is analyzed,and the result demonstrates the effectiveness of the method.
引文
[1]佘高波.在航空型号研制中引入项目管理产生的冲突与解决思路[J].航空科学技术,2004(4):15-17.
    [2]徐汉川.一种结合设计BOM/BOP的制造BOM的生成方法[J].中国机械工程,2005,16(8):701-705.
    [3]Hayes R D.Analysis and application of earned value management to the naval construction force[D].The Faculty of The School of Civil Engineering Purdue University West Lafayette,Indiana,2001-06.
    [4]李庆华.中国网络计划技术大全[M].北京:地震出版社,1993.
    [5]邢莉燕,李纪成.动态规划法在网络成本工期优化中的应用[J].山东科学,1998,11(3):60-64.
    [6]Fleming Q W.The earned value body of knowledge[R].Acquisition Resources&Analysis/Acquisition Management,2002-09.
    [7]Wilkens T T.Earnd value,clear and simple[R].Los Angeles Country Metropolitan Transportation Authority,1999-04.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心