大断面巷道交叉点破坏机理分析及支护研究
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
为了解决马钢集团和睦山铁矿区大断面巷道交叉点支护困难的工程问题,对该矿巷道破坏情况进行了调查和研究。利用电子显微视频仪发现了造成岩石局部局部应力集中及破坏的岩石包体特殊结构,查明了巷道破坏的原因。在此基础上,提出了锚网喷一次支护,锚注与锚索联合二次加强支护的复合支护方案。利用ABAQUS非线性有限元软件模拟分析了锚注联合支护的作用机理,数值计算结果验证了支护方案的合理性。现场施工监测表明,采用联合支护方案后巷道交岔点处围岩变形趋于稳定,两帮累计位移最终为20 mm左右,取得了良好支护效果。
In order to solve the problem in supporting cross roadway with large span in Hemushan mining area of Maanshan Steel Group,the roadway destruction was investigated.A special inclusions structure which can cause local stress concentration and failure in rock was observed by video microscope.And the damage reasons of roadway were found out.On the basis of these,a composite support scheme of bolt-steel mesh-shotcreting for the first flexible support and bolting-grouting and pre-stressed anchor cable for the secondary fortified support was designed.Simulation analysis was made on the supporting mechanism of the combination of bolt,shotcreting,steel mesh and grouting by nonlinear finite element software ABAQUS,and the results of numerical calculation proved the combined support scheme to be rational.The monitored results of case engineering show that the deformation of surrounding rock at the cross roadway tended to be stable,the accumulative displacement of surrounding rock among two sides of the cross roadway was in the range of 20mm,resulting in good effect of support.
引文
[1]刘红岗,韩立军,贺永年.松软泥岩巷道大冒顶综合治理技术的研究[J].金属矿山,2006,(8):8~12.
    [2]韩立军,王延宁,周胜利.软弱岩层中大断面巷道施工与支护技术研究[J].金属矿山,2006,(11):23~26.
    [3]李国臣,张希平,李茂东,等.交岔点冒顶事故分析与处理[J].矿山压力与顶板管理,2001,(2):55~58.
    [4]许昭永,王彬,赵晋明,等.含硬包体试样微破裂图象演变过程的实验研究[J].地震学报,1997,19(3)317~322.
    [5]刘庭金,唐春安,朱合华.低弹模包体强度对试样破裂模式影响的数值试验[J].同济大学学报,2002,30(3):263~268.
    [6]朱以文,蔡元奇,许晗,等.ABAQUS与岩土工程分析[M].香港:中国图书出版社,2005.
    [7]董方庭.巷道围岩松动圈支护理论及应用技术[M].北京:煤炭工业出版社,2001:59~80.
    [8]刘传孝.新汶华丰矿井巷松动圈探地雷达施测研究[J].应用基础与工程科学学报,1999,7(2):171~176.
    [9]靖洪文,宋宏伟,郭志宏.软岩巷道围岩松动圈变形机理及控制技术研究[J].中国矿业大学学报,1999,28(6):560~564.

版权所有:© 2023 中国地质图书馆 中国地质调查局地学文献中心