隧洞穿过活动断裂抗震防震问题研究方法探讨
详细信息 本馆镜像全文    |  推荐本文 | | 获取馆网全文
摘要
通过工程实例提出动态方法研究隧洞穿过活动断裂的防震抗震问题,首先通过地表探槽和钻探初步判断活动断裂与隧洞相交的宏观位置;第二根据开挖揭露的断层性状,确定最新活动断裂的出露桩号;第三再通过施工地质编录资料研究抗震防震方案。
The paper proposes a dynamic method to study the earthquake-preparedness and earthquake-resistance problems by project cases.The method has three phases,the first phase is determination of the intersection location of active fault and tunnel by using trial trench and borehole;the second phase is determination of the stake number of the active fault by the characteristics revealed by excavation;the third phase is determination of the scheme of earthquake-preparedness and earthquake-resistance by construction geological logging.
引文
[1]徐锡伟,等.活动断层地震灾害预测方法与应用[M].北京:科技出版社,2011.
    [2]胡聿贤.地震安全性评价技术教程[M].第二版.北京:地震出版社,2003.
    [3]武汉测绘学院测量学编写组.测量学[M].北京:测绘出版社,1979.
    [4]赵伯明,等.汶川Ms8.0地震断层与地震灾害初步分析[J].地震地质,2008,30(4):839-851.
    [5]李细光,等.汶川Ms8.0地震基岩中的地表破裂[J].地震地质,2008,30(4):989-992.