海洋工程建造计划编制和进度控制研究
详细信息    本馆镜像全文|  推荐本文 |  |   获取CNKI官网全文
摘要
海洋工程计划编制与进度控制的基本职能是编制工程项目总体计划、月周计
    划,并在项目运行过程中对计划进行跟踪,确保项目按里程碑点正常运行,最终
    按合同工期完工。
    本论文以渤中 25-1B、D、E 导管架陆地建造计划编制和进度控制研究为基
    础,运用定额原理、施工组织管理学、工程项目管理学、流水施工法、网络计划
    技术和计算机与可编程控制器等工具,借鉴了国内外先进的施工经验,在工时定
    额、工序关系、工期和资源优化、进度控制等方面进行了一些探索和研究,这些
    研究成果在多个项目施工中得到了应用,缩短了工期,降低了成本。
The basic function of offshore engineering plan and progress control is for the
    establishment of project general plan and monthly plan and weekly plan, and traces to
    the plan during plan execution and ensures that project is smoothly executed
    following the milestone and is completed on time as the contract.
     This paper is a study for the establishment of onshore fabrication plan and
    progress control of BZ25-1 B,D,E jackets and uses ration principle, construction
    organization principle, project management, flow process method and uses the
    reference of domestic and foreign advanced construction experiences to do some
    research and study of man-hour ration, process sequence relationship, time limit,
    resource optimization, progress control. The study has been applied in several projects,
    which shortens construction time and decreases cost.
引文
[1] 齐宝库主编,丛培主审:工程项目管理。大连理工出版社,1999。
    [2] 江景波、赵志缙等编著:建筑施工。同济大学出版社,1989。
    [3] 全国建筑施工企业项目经理培训教材编写委员会编著:施工组织设计进度
     管理,1999。
    [4] 杨劲主编:建筑工程定额原理与概预算。中国建筑工业出版社,1991。
    [5] 郎荣燊、刘荔娟主编:现代项目管理学。天津大学出版社,1997。
    [6] 浙江大学数学系高等数学教研组编:概率论与数理统计。高等教育出版社,
     1989