摘要
This paper introduced the main achievements of “key technology and equipment of 2 000 m core drilling” in the “863” project: integration of drilling equipment and core drilling apparatus has been completed to form the ability of deep core drilling construction and demonstration. The specific project of crisis mine ZK43-1 construction in Jinqingding mine was finished with good borehole quality of termination depth 2 212.80 m, average drilling efficiency 1.65 m/h and core recovery 98.6%. In this borehole construction, 3 pieces of record of depth in drilling and casing in China were created. And some experiences were accumulated.