摘要
结合上海诸光路隧道工程,文章对盾构隧道内部双层预制结构体系的现场拼装关键技术进行了分析,主要包括构件的精确定位、接头的处理、专用设备的开发、施工机械的合理选取以及吊装技巧等。通过现场拼装发现立柱预留插筋的准确定位是拼装成功的关键,立柱和车道板的安装关键在于微调,微调需要开发专用设备才能满足精度需求。
Combined with Zhuguang road tunnel project in Shanghai,the key technology of field assembly of double-deck prefabricated structure system in shield tunnels is analyzed,including precise positioning of components, treatment of joints, development of special equipment, reasonable selection of construction machinery and hoisting techniques. It is found that the accurate positioning of the reserved column stiffeners is the key to the success of assembling. The installation and fine-tuning of the columns and lane boards need to develop special equipment to meet the accuracy requirements.
引文
[1]周松.上海复兴东路越江隧道工程施工技术综述[J].岩石力学与工程学报,2004,23(S2):4761-4769.ZHOU Song. Review on Construction Technology for Fuxingdonglu Crossing-River Tunnel Project in Shanghai[J]. Chinese Journal of Rock Mechanics and Engineering,2004,23(S2):4761-4769.
[2]周文波,吴惠明.水底公路隧道盾构掘进中的道路同步施工技术[J].现代隧道技术,1998,(3):13-17.ZHOU Wenbo,WU Huiming. Synchronous Construction Technology of Pavement Building and Shield Tunnelling in an Underriver Highway Tunnel[J]. Modern Tunnelling Technology, 1998,(3):13-17.
[3]黄俊,马明,李勇,等.盾构隧道内部双层结构快速化施工方法技术研究[J].公路,2013,(3):212-219.HUANG Jun,MA Ming,LI Yong,et al. Research on Technology for Rapid Construction Method of Double Deck in Large Diameter Shield Tunnel[J]. Highway,2013,(3):212-219.
[4]晏胜荣.单管双层盾构隧道内部结构同步施工台车设计与制造技术[J].铁道建筑技术,2015,(2):82-85.YAN Shengrong. Design and Manufacturing Technology for Synchronized Construction Trolley in Single Tube Double Internal Structure of Shield Tunnel[J]. Railway Construction Technology,2015,(2):82-85.
[5]拓勇飞,郭小红.南京纬三路过江通道总体设计与关键技术[J].现代隧道技术,2015,52(4):1-6.TUO Yongfei,GUO Xiaohong. General Design and Key Technologies of the Nanjing Weisan Road River-Crossing Tunnel Project[J]. Modem Tunnelling Technology,2015,52(4):1-6.
[6]胡滢之.双层双向盾构法隧道横断面的创新设计[J].中国市政工程,2010,(S1):1-3.HU Yingzhi. On an Innovation of Tunnel Cross Section Design of Double-deck&Double-direction Shield Method[J]. China Municipal Engineering,2010,(S1):1-3.
[7]王善高,史世波,舒恒,等.单管双层特长盾构隧道内部结构预制施工技术——以南京纬三路过江盾构隧道工程为例[J].隧道建设,2016,36(4):451-457.WANG Shangao,SHI Shibo,SHU Heng,et al. Precasting Technologies for Internal Structure of Single-tube Double-deck Extra-long Shield Tunnel:A Case Study on Yangtze River-crossing Shield Tunnel on Weisan Road in Nanjing[J]. Tunnel Construction,2016,36(4):451-457.