摘要
溪洛渡水电站库周是地灾多发地区,项目业主中国长法三峡集团公司和地方政府在水库蓄水初期开展群测群防工作,取得了一定的成效。为此,描述了溪洛渡水电站水库影响区群测群防工作的历史背景,决策过程,介绍了群测群防工作时限、工作范围、工作方案、人员配置、责任分工及费用来源等内容,总结了工作实施取得的成效,并针对水库影响区(地质灾害预测预防)群防群测工作提出了建议。
The area around the reservoir of Xiluodu Hydropower Station is a disaster-prone area. To prevent geological disasters,China Three Gorges Corporation and local governments have carried out mass monitoring and preventing of geological disasters in the early stage of reservoir impoundment,and achieved some successes. The historical background of mass monitoring and preventing and the process of decision-making are introduced,and the schedule,scope,staffing and fund source of mass monitoring and preventing are also introduced herein. According to the experiences of mass monitoring and preventing of geological disasters in Xiluodu Hydropower Station,some suggestions on mass monitoring and preventing of geological disasters in reservoir influence area are put forward.
引文
[1]孙仁先,江鸿彬,石长柏.三峡库区秭归县地质灾害发育规律与“群测群防”防治[J].湖北地矿,2002(4):70-73.
[2]贠小苏.地质灾害群测群防体系建设指南[M].北京:中国大地出版社,2008.
[3]国务院令第394号地质灾害防治条例[S].
[4]徐潇宇.三峡库区地质灾害防治系统运行机制研究[D].北京:中国地质大学,2013.
[5]季伟峰.三峡库区三期地质灾害防治监测预警的主要方法[J].探矿工程(岩土钻掘工程),2008(7):14-17.
[6]薛宁波、马清文、王成华.地质灾害易发山区群测群防体系与突发性灾害预警[J].中国水土保持科学,2008(S1):12-15.