摘要
Hubei Laifeng Kaidi power plant site area has complicated engineering geology condition. Therefore, the paper carried on engineering geological exploration work at feasibility stage and identified basically about the landform, the condition of meteorology and hydrology, characteristics of geological structure and bad geological phenomenon of the proposed site, as well as buried distribution, lithologic characteristics and main physical and mechanical properties in exploration depth range of proposed site. It determined seismic fortification intensity of the proposed site and divided the type of site soil and the classification of construction site. During the work, the different distribution area of main plant area, open fuel yard and area of ash comprehensive utilization were carried out drilling exploration. It conducted stability analysis and selection of foundation type in bad geological condition of different distribution area, and proposed control measures.