三峡工程碾压混凝土围堰施工若干重大技术问题研究
详细信息   下载全文 | 推荐本文 |
摘要
本文系统地介绍了三峡工程中的关键项目之一碾压混凝土围堰施工过程中若干重大技术问题的研究成果。这一项目工期紧、施工强度大、技术要求高 ,施工采用全断面摊铺碾压、不间断连续上升方式 ,创造了最高月强度 47 6万m3,最高日强度 2 1万m3,最高小时强度达到 12 65m3等多项碾压混凝土施工史上的新纪录。本文的研究成果对其它类似工程的实施有一定的借鉴作用
        The research results of the key techniques for roller compacted concrete(RCC) cofferdam construction of the Three Gorges Project(TGP) are presented in this paper.The RCC cofferdam construction of TGP was featuring tight schedule,high intensity and strict technical requirements.By means of full face spreading roller compaction,the RCC cofferdam grew up in a continuous manner with a number of records in the history of RCC construction,such as monthly pouring record of 476,000m\+3,daily record of 21,000m\+3 and hourly record of 1,265m\+3.The research result of RCC cofferdam construction of TGP may be available for the references to other similar projects.
引文
[1] 郑守仁.三峡工程三期围堰及截流设计关键技术问题[J].人民长江,2003,33(1):7~10.
    [2] 王毅,张驽.三峡工程三期碾压混凝土围堰快速施工研究[J].中国三峡建设,2002,(10):23~25.
    [3] 朱忠平,韩炳兰.三期RCC围堰工程翻转模板设计与施工[J].中国三峡工程建设,2003,5.
    [4] 滕东海,李善平.三峡三期RCC围堰施工质量管理与控制[J].中国三峡工程建设,2003,5.
    [5] 曹广晶,彭冈.三峡二期厂坝工程混凝土施工质量控制[J].水力发电,2002,(6):38~42.
    [6] 谭靖夷编.中国水力发电工程(施工卷)[M].北京:中国电力出版社,2000,8.
目录

© 2004-2018 中国地质图书馆版权所有 京ICP备05064691号 京公网安备11010802017129号

地址:北京市海淀区学院路29号 邮编:100083

电话:办公室:(+86 10)66554848;文献借阅、咨询服务、科技查新:66554700