High-level integrated deterministic, stochastic and fuzzy cost-duration analysis aids project planning and monitoring, focusing on uncertainties and earned value metrics
详细信息    查看全文
文摘
Cost-duration network analysis of facilities projects developed around high-level work breakdown progress diagrams. Deterministic, fuzzy and stochastic analysis integrated to provide insight to different facets of cost-duration uncertainty. Critical path focus to earned duration analysis providing to-completion duration forecasts linked to work item criticality. Calibrating fuzzy and stochastic analysis to provide comparable cost-duration progress and to-completion forecasts. Improving the reliability of to-completion forecasts by selecting metrics with low mean absolute percentage errors.