摘要
2014年第四季度停产期间,采用了有效的工作面设备、顶板及采空区管理技术。针对顶板压力变大,采高变低和采空区煤炭氧化自燃问题,采取"小推进"和"大推进"相结合的治理措施,成功实现了工作面在停产期间的安全过渡。
Effective mining face equipment along with the management technology of roof and goaf were established during the production halt of the fourth quarter in 2014. On the issue of roof pressure becoming larger,mining height becoming lower and coal spontaneous of the mined-out regions,"small push "and "great advace"were combined. As a result the safety transition of mining face during the production halt was successfully achieved.
引文
[1]郭凡进.复合煤层开采防止采空区自燃综合技术[J].煤炭工程,2008,39(6):62-64.
[2]张志军.大采高超长工作面顶板灾害预警研究[D].山西.太原理工大学,2010:8-9.
[3]史全忠,陈广喜,李胜,等.关于综采工作面破碎顶板控制的研究[J].采矿技术,2008,8(3):22-24.
[4]罗伙根,张增辉.保德煤矿81304综放工作面上隅角瓦斯治理[J].煤矿安全,2012,43(9):126-128.