摘要
论述了大型斜拉桥高塔柱上索道管锚垫板与出壁口中心点位的精密测定方法,概述了索道管安装测量定位的一般流程,详细介绍了全站仪自由设站法和间接高差传递法分别精确测定索道管测控点平面坐标与高程的过程及计算方法,并进行了相应的精度分析。理论与实践均证明,本文提出的方法与一般的极坐标测量法相比,索道管安装测控精度更高,测控更加方便、快捷、灵活,可广泛应用于现代斜拉桥索道管和钢锚梁安装定位中。
In this paper,the precise position method for the center point of cable duck's anchor plate and wall outlet of large cable stayed bridge is discussed; The general process of measurement and location of cableway pipe installation is summarized; The plane coordinate and elevation of cable duck's observe and control point are determined by the total station's free station method and indirect height difference transfer method respectively. So this paper also introduced the process and calculation method and analyzed the corresponding accuracy. The theory and practice have proved that the method proposed in this paper is more accurate and easy to measure and control than the general polar coordinate measuring method,so it is recommended to be popularized and applied in the installation and positioning of the cable pipe and steel anchor beam of modern cable-stayed bridges.
引文
[1]邓泽宜,彭文武.大型斜拉桥高塔柱索道管精密定位测量方法分析[J].华南港工,2007(2):70-73,82.
[2]张海岐.斜拉桥索道管空间多点定位技术研究探讨[J].湖南交通科技,2006(4):82-84.
[3]唐佑辉,李更召,周帆,等.大型斜拉桥索道管初定位及精密定位测量方法研究[J].勘察科学技术,2017(1):24-27.
[4]李晓华,刘为东,黄博,等.一种改进的斜拉桥索道管精密定位方法[J].测绘地理信息,2013,38(2):63-65.
[5]王磊,刘成龙,杨雪峰,等.高速铁路自由设站三维整体平差计算及精度评定[J].测绘科学技术学报,2011,28(4):258-261.
[6]杨元喜.抗差估计理论及其应用[M].北京:八一出版社,1993.
[7]中华人民共和国铁道部.TB 10601-2009高速铁路工程测量规范[S].北京:中国铁道出版社,2010.