针对已建枢纽扩建船闸工程施工围堰标准的问题,结合株洲二线船闸工程对围堰的双重使用功能进行分析,其施工围堰应分区确定围堰标准,并在充分权衡导流设施建设成本与降低标准造成损失的基础上,妥善安排度汛、排水措施,将对工期的影响降到最低。同时总结了船闸扩建工程施工导流特点、围堰设计目标、过水围堰度汛时的主要工程措施,为航电枢纽船闸改扩建工程的布置和围堰设计提供参考。
Aiming at the construction cofferdam standard of ship lock expansion project,we analyze double functions of the cofferdam based on Zhuzhou second ship lock project. The standard of cofferdam should be determined for different regions. Based on fully balancing the construction cost of diversion facilities and the loss caused by reducing standards,the flood control and storm water drainage are appropriately implemented to minimize the impact on the duration of the project.Meanwhile,we summarize the characteristics of construction diversion,the design targets of the cofferdam and the flood control measures,which can provide references to new arrangement schemes and cofferdam design for ship lock expansion project.
引文
[1]中交水运规划设计院有限公司.湘江二级航道二期工程株洲航电枢纽二线船闸工程初步设计[R].北京:中交水运规划设计院有限公司,2015.
[2]中交水运规划设计院有限公司.湘江二级航道二期工程勘察设计B合同标段岩土工程勘察报告[R].北京:中交水运规划设计院有限公司,2014.
[3]康世荣,陈东山.水利水电工程施工组织设计手册[M].北京:中国水利水电出版社,1996.
[4]中水东北勘测设计研究有限责任公司.水利水电工程施工组织设计规范:SL 303—2004[S].北京:中国水利水电出版社,2004.
[5]中交水运规划设计院有限公司.株洲航电枢纽二线船闸工程两线船闸间坝体及高喷防渗墙实施方案专题研究报告[R].北京:中交水运规划设计院有限公司,2016.