摘要
该文以一栋六层宿舍楼为例,对预制装配整体式混凝土框架结构的结构设计方法、楼板选择、连接节点、设计和施工中应注意的事项等进行了详细论述。由于国内类似工程的设计和施工经验不足,对这种新型技术的研究,旨在推动这种结构的发展,相关方法和思路可为类似的工程提供参考。
With a six-storeydormitory building as a case study, this paper elaborates the structural design methods, floor selection, nodes, design and noteworthy issues in construction of the integral prefabricated concrete frame structure. Owing to the lack of design and construction experience for similar domestic engineering, the study on this new technology aims to facilitate the development of the structure. Relevant methods and thoughts can be referenced.