结合重庆来福士广场空中连廊铝板单元整体安装过程,介绍铝板单元体V形钢架组装、胎架安装、铝板面层组装、液压同步吊装及单元体就位固定的整个过程。液压同步吊装过程详细介绍了提升吊点设置、起吊角度控制、吊装防风措施、液压提升力控制、液压同步提升控制等技术要点,高空单元体整体吊装质量、进度、安全、措施成本得到了保障,取得了很好效果。
Combined with the integral installation process of air corridor aluminium plate unit in Chongqing Raffles City, the whole process of V-shaped steel frame assembly, frame installation,aluminium plate surface assembly,hydraulic synchronous hoisting and unit positioning and fixing are introduced. In the process of hydraulic synchronous hoisting,the technical points of hoisting point setting, hoisting angle control, hoisting windproof measures, hydraulic hoisting force control and hydraulic synchronous hoisting control are introduced in detail. The integral hoisting quality,progress,safety and cost of measures are guaranteed and good results are achieved.
引文
[1]周瑜,林张欢.武汉绿地中心微倾折线型伸臂-环带桁架施工技术[J].施工技术,2018,47(15):95-98.
[2]范广军,谷洋,向峰,等.忠县电竞场馆超长主次桁架与环带桁架穹顶钢结构施工技术[J].施工技术,2018,47(11):26-30.
[3]罗艺,陈鹏,郑志辉,等.大跨度悬挑管桁架结构施工技术[J].施工技术,2018,47(11):144-145.
[4]程志军,党宗盛,蓝振芳.腾讯滨海大厦核心筒大跨度液压爬升安全防护平台施工技术[J].施工技术,2018,47(8):41-44.
[5]宁华宏,唐际宇,唐阁威,等.南宁华润中心东写字楼桁架层施工技术[J].施工技术,2018,47(4):25-28.
[6]曾文涛,崔志勇,陈建龙,等.广发证券大厦屋顶大跨度钢结构门架施工技术[J].施工技术,2018,47(2):4-8,13.
[7]上海建工股份有限公司,同济大学.重型结构和设备整体提升技术规范:GB51162—2016[S].北京:中国计划出版社,2016.
[8]中国建筑科学研究院.建筑工程施工质量验收统一标准:GB50300—2013[S].北京:中国建筑工业出版社,2014.
[9]上海市建工设计研究院有限公司,南通市达欣工程股份有限公司.建筑施工高处作业安全技术规范:JGJ80—2016[S].北京:中国建筑工业出版社,2016.
[10]天津市建工工程总承包有限公司,中启胶建集团有限公司.建筑施工安全检查标准:JGJ59—2011[S].北京:中国建筑工业出版社,2012.