红庆梁煤矿冻结井筒壁间注浆时机研究
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Study on Grouting Time of Mine Freezing Shaft Liner in Hongqingliang Mine
  • 作者:任强 ; 高伟 ; 彭伟 ; 吴光辉
  • 英文作者:REN Qiang;GAO Wei;PENG Wei;WU Guang-hui;Ordos Haohua Hongqingliang Mining Industry Company Limited;Tiandi Science and Technology Company Limited;China Coal 71st Engineering Department;
  • 关键词:冻结凿井法 ; 壁间注浆 ; 温度监测 ; 注浆时机
  • 英文关键词:mine freezing shaft sinking method;;grouting in mine shaft liner;;temperature monitoring and measuring;;grouting time
  • 中文刊名:MKSJ
  • 英文刊名:Coal Engineering
  • 机构:鄂尔多斯市昊华红庆梁矿业有限公司;天地科技股份有限公司;中煤第七十一工程处;
  • 出版日期:2014-11-07 10:29
  • 出版单位:煤炭工程
  • 年:2014
  • 期:v.46;No.437
  • 语种:中文;
  • 页:MKSJ201410034
  • 页数:3
  • CN:10
  • ISSN:11-4658/TD
  • 分类号:139-141
摘要
为了确保壁间注浆效果,提高壁间密实度,分析冻结井筒壁间注浆的合理时机,对红庆梁煤矿风井井壁壁间温度进行监测,并根据混凝土井壁强度增长规律对壁间注浆压力进行了计算,结果表明:在井帮温度控制在4~6℃的情况下,套壁结束后20d范围内整个井筒壁间均能达到4℃以上,此时下部井壁已浇筑至少28d以上,井壁结构强度能够达到设计强度,能够承受计算壁间注浆压力,认为在冻结施工过程中应该进行井帮温度控制,套壁结束后进行壁间注浆时机最佳。
        In order to ensure a grouting effect in a mine shaft liner and to improve the compaction of the mine shaft liner,the paper analyzed the rational grouting time of the mine freezing shaft liner and a monitoring and measurement was conducted on the liner temperature of the mine ventilation shaft liner in Hongqingliang Mine. According to the strength increased law of the concrete shaft liner,calculation was conducted on the grouting pressure of the mine shaft liner. The results showed that when the temperature of the mine shaft liner could be controlled at 4 ~ 6℃,within 20 days after the mine shaft lining completed,the temperature of the whole mine shaft liner was over 4℃. At this moment,the bottom part of the mine shaft liner was lined at less over 28 days; the strength of the mine shaft liner structure could reach the designed strength and could bear the calculated grouting pressure of the mine shaft liner. The paper hold that during the freezing construction period,the temperature of the mine shaft liner should be controlled and a optimized grouting time of the mine shaft liner could be conducted when the mine shaft lining operation completed.
引文
[1]贾翱翔.冻结法凿井井壁结构的探讨[J].煤炭工程,2006(2):63-65.
    [2]方根生.丁集矿深井冻结井壁渗水的治理措施[J].煤炭工程,2010,42(6):27-29.
    [3]盛天宝.深厚冻结井壁壁间前注浆机理与应用[J].煤炭学报,2009(7):912-916.
    [4]张荣立,何国纬,李铎,等.采矿工程设计手册[M].北京:煤炭工业出版社,2002.
    [5]杨晓玲.壁间注浆在平禹九矿副立井井筒中的应用[J].中州煤炭,2013(7):88-89,92.
    [6]王海军.浅谈冻结段壁后及壁间注浆封堵地层水[J].中州煤炭,2009(6):99-100.
    [7]李立权.混凝土配合比设计手册[M].广东:华南理工大学出版社,2003.
    [8]张永成,董书宁.矿井注浆施工手册[M].北京:煤炭工业出版社,2013.