摘要
结合工程实际,在其深基坑施工中采用了传力杆式内支撑转换施工工艺,即用钢筋混凝土换撑梁传力杆代替了原有回填土和混凝土板带的换撑方式。从实践效果来看:该工艺受空间限制较小,工序简单,可缩短换撑周期,使地下主体结构能够连续施工,无需等待外墙防水施工和回填土的时间,大大节约了工期。
Combined with the engineering practice, the construction technology of the dowel bar type internal support conversion was adopted in the construction of the deep foundation pit, namely, the dowel bar of reinforced concrete support replacement beam was used to replace the original backfill soil and the concrete slab belt. From the practical effect: the process was simple and less limited by space, so that the cycle of the support replacement could be shortened, and the underground main structure could be continuously constructed without waiting for the waterproof construction of the external wall and the time of backfilling, and greatly saved the construction period.