摘要
江仓一号井位于海拔3800m的青藏高原上,天气寒冷,空气稀薄,施工难度大。为了加快施工进度,从设备选用、保温措施、注浆治水等多方面采取措施,促进了矿井快速施工,月进度在60m以上,最高单进达76m,实现了高原高寒地区大倾角斜井快速施工。
Jiangcang No. 1 shaft was at 3, 800 m above sea level on the qinghai- tibet plateau, the weather was cold, thin air,the construction was difficult. In order to speed up the construction progress, from equipment selection, heat preservation measures, grouting water control measures in many aspects, promoted the rapid construction of mine, month progress was more than 60 m, the highest single into 76 m, implemented highland alpine region shaft with large angle of inclination rapid construction.