摘要
以实际矿井回风顺槽煤巷掘进施工为例,阐述了大断面煤巷快速掘进存在的难题,分析了影响矿井快速掘进的主要因素,针对性地提出了大断面煤巷快速掘进支护的优化措施。实践证明,优化后的大断面煤巷掘进施工速度和效率得到大幅度的提升,巷道成形质量和围岩稳定性都得到了很好的控制。
Taking the actual coal roadway excavation construction of the mine air returning crossheading as an example, this paper expounded the problems of rapid excavation of large-section coal roadway, analyzed the main factors affecting the rapid excavation of the mine and proposed the optimization measures of rapid excavation support of large-section coal roadway. Practice has proved that the optimized construction speed and efficiency of large-section coal roadway excavation has been greatly improved,and the roadway forming quality and surrounding rock stability have been well controlled.
引文
[1]郝文印.大断面煤巷快速掘进支护技术研究[J].煤矿现代化,2018(5):27-29.
[2]高慧琪.大断面煤巷掘进技术优化及实践[J].煤炭与化工,2017,40(10):23-26.
[3]朱现磊,杨仁树,宫全红.大断面煤巷快速掘进影响因素及技术优化[J].煤炭工程,2015,47(7):43-45.
[4]金元甲,高升.高瓦斯矿井厚煤层大断面巷道快速掘进技术[J].煤炭工程,2014,46(9):49-51.
[5]聂晓飞,闫高峰,宋育刚,等.大断面煤巷快速掘进技术[J].煤炭科学技术,2013,41(增刊2):141-142.
[6]杜启军,赵启峰,杨壮,等.复杂地质条件下大断面煤巷快速掘进研究与实践[J].煤炭工程,2013,45(6):76-79.
[7]马长乐,袁龙飞,张羽,等.大断面煤巷快速掘进施工工艺[J].煤矿安全,2013,44(5):98-100.