挑流丁坝在海港工程中的应用
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Application of spur dike in seaport engineering
  • 作者:米刘芳
  • 英文作者:MI Liu-fang;Tianjin Port & Channel Engineering Co.,Ltd.;
  • 关键词:挑流丁坝 ; 辐射沙洲 ; 潮沟 ; 促淤保滩 ; 沿堤流
  • 英文关键词:spur dike;;sand ridge region;;tidal creek;;beach protection and siltation promotion;;current along cofferdam
  • 中文刊名:GKGC
  • 英文刊名:China Harbour Engineering
  • 机构:天津港航工程有限公司;
  • 出版日期:2018-07-25
  • 出版单位:中国港湾建设
  • 年:2018
  • 期:v.38;No.245
  • 语种:中文;
  • 页:GKGC201807011
  • 页数:4
  • CN:07
  • ISSN:12-1310/U
  • 分类号:55-58
摘要
结合如东县小洋口(洋口镇)重装设备成套基地项目工程实例,对挑流丁坝在辐射沙州地区海港工程中,维护引堤、护岸围埝堤身稳定与安全进行了应用研究。结果表明,挑流丁坝的建设实现了促淤保滩,防止潮沟水平迁移,阻断潮沟落潮流对堤身的冲击与掏蚀,改变沿堤流的流向,使之与堤身保持一定的安全距离,对工程安全建设起到了重要作用。
        Based on the heavy equipment installation complete basement project in Xiaoyangkou( Yangkou Town) of Rudong County, we conducted the application research of stability and safety of approach dike maintenance and cofferdam during the construction of the seaport in the radial sand ridge region. The results show that the construction of the spur dike has promoted the deposition and protected the beach, prevented the horizontal migration of tidal creeks, stopped the impact and erosion of current in the tidal creeks on the cofferdam, and changed the current direction along the cofferdam so that to maintain a certain distance with the cofferdam which has played an role of great importance in safely constructing the project.
引文
[1]罗肇森.潮汐通道口拦门沙航道的淤积计算[J].海洋工程,1992,10(2):32-40.LUO Zhao-sen.Prediction of sedimentation for the navigation channel of a tidal inlet with mouth bar[J].The Ocean Engineering,1992,10(2):32-40.
    [2]曹祖德.海床的冲淤分析计算[R].天津:交通部天津水运工程科学研究所,2006.CAO Zu-de.Analysis and calculation of the scouring and silting of the seabed[R].Tianjin:Tianjin Research Institute of Water Transport Engineering,M.O.T.,2006.
    [3]曹祖德,李蓓,孔令双.波、流共存时的水体挟沙力[J].水道港口,2001,22(4):151-155.CAO Zu-de,LI Bei,KONG Ling-shuang.Carrying capacity for a wave-current coexistent system[J].Journal of Waterway and Harbour,2001,22(4):151-155.
    [4]杨树森,韩西军.南通港洋口港区人工岛工程整体稳定性综合研究[R].天津:交通部天津水运工程科学研究所,2006.YANG Shu-sen,HAN Xi-jun.Comprehensive stability study of artificial island project in Nantong port area[R].Tianjin:Tianjin Research Institute of Water Transport Engineering,M.O.T.,2006.
    [5]李孟国,杨树森,韩西军.江苏南通港洋口港区人工岛工程潮流泥沙数学模型研究[R].天津:交通部天津水运工程科学研究所,2005.LI Meng-guo,YANG Shu-sen,HAN Xi-jun.Study on tidal current and sediment mathematical model for artificial island in Nantong port of Jiangsu[R].Tianjin:Tianjin Research Institute of Water Transport Engineering,M.O.T.,2005.
    [6]秦崇仁,肖波,高学平.波浪水流共同作用下人工岛周围局部冲刷的研究[J].海洋学报,1994,16(3):130-138.QIN Chong-ren,XIAO Bo,GAO Xue-ping.Study on local scour around artificial island under combined action of wave and current[J].Acta Oceanologica Sinica,1994,16(3):130-138.
    [7]韩西军,杨树森,陈汉宝.南通港洋口港区陆岛通道工程桥墩冲刷波浪水槽试验研究报告[R].天津:交通部天津水运工程科学研究所,2005.HAN Xi-jun,YANG Shu-sen,CHEN Han-bao.Study on tidal current and sediment mathematical model for artificial island in Nantong port of Jiangsu[R].Tianjin:Tianjin Research Institute of Water Transport Engineering,M.O.T.,2005.
    [8]杨树森,陈汉宝,韩西军,等.江苏LNG项目接收站配套码头工程人工岛周边在海洋动力作用下冲淤动床泥沙物理模型试验研究报告[R].天津:交通部天津水运工程科学研究所,2005.YANG Shu-sen,CHEN Han-bao,HAN Xi-jun,et al.Physical model test study on silt moving bed of artificial island around artificial island in Jiangsu LNG project receiving terminal[R].Tianjin:Tianjin Research Institute of Water Transport Engineering,M.O.T.,2005.

© 2004-2018 中国地质图书馆版权所有 京ICP备05064691号 京公网安备11010802017129号