超前灌浆参数设计及其加固防渗效果的数值分析
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Numerical Analysis of Design of Pre-grouting Parameters and Effect of Reinforcement and Seepage Control
  • 作者:祁舒燕 ; 肖明
  • 英文作者:QI Shu-yan;XIAO Ming;State Key Laboratory of Water Resources and Hydropower Engineering Science,Wuhan University;Key Laboratory of Rock Mechanics in Hydraulic Structural Engineering,Ministry of Education,Wuhan University;
  • 关键词:超前灌浆 ; 参数设计 ; 加固防渗 ; 数值分析
  • 英文关键词:pre-grouting;;parameter design;;reinforcement and seepage control;;numerical analysis
  • 中文刊名:SDNY
  • 英文刊名:Water Resources and Power
  • 机构:武汉大学水资源与水电工程科学国家重点实验室;武汉大学水工岩石力学教育部重点实验室;
  • 出版日期:2017-09-25
  • 出版单位:水电能源科学
  • 年:2017
  • 期:v.35;No.205
  • 基金:国家重点基础研究计划(973)项目(2015CB057904);; 国家自然科学基金重大研究计划(51579191)
  • 语种:中文;
  • 页:SDNY201709028
  • 页数:4
  • CN:09
  • ISSN:42-1231/TK
  • 分类号:112-115
摘要
鉴于地下水丰富且地质条件复杂洞段采用超前灌浆技术是解决涌水突砂和加固围岩效果较好的工程措施。选取滇中引水隧洞高埋深、高水头、Ⅳ类围岩段为例,采用数值分析的方法探讨了超前灌浆深度的合理化选取,并对比分析了有无超前灌浆下洞周围岩的加固和防渗效果。结果表明,与无超前灌浆相比,在合理的灌浆深度下洞周围岩的变形量和破坏深度及隧洞的渗水量均明显减小,超前灌浆达到了加固围岩和防渗的双重效果,为实际施工中遇到类似问题提供了切实可行的建议。
        In view of the abundant groundwater and complex geological conditions of the tunnel,pre-grouting technology is one of the good engineering measures to solve sudden gushing sand and reinforce rock mass.This paper takes Yunnan diversion tunnel with high buried depth,high water head and IV surrounding rock as an example,and explores the reasonable selection of pre-grouting depth by using the numerical analysis method and compares the reinforcement and anti-seepage effect of the surrounding rock in the conditions of with and without pre-grouting.Compared with no pre-grouting,the results show that the deformation and failure depth of the surrounding rock and the quantity of water flow of the tunnel are reduced significantly under a reasonable grouting depth.Pre-grouting achieves a double effect of surrounding rock reinforcement and seepage control,which provides practical suggestions for the construction of similar actual projects.
引文
[1]潘罗华,孙金山,张明燕.山岭隧道掘进机施工超前灌浆技术[J].黑龙江水利科技,2008,36(2):35-36.
    [2]肖明.地下洞室施工开挖三维动态过程数值模拟分析[J].岩土工程学报,2000,22(4):421-425.
    [3]王明,肖明,李凌子.裂隙岩体渗流作用下地下洞室围岩稳定性分析[J].水电能源科学,2015,33(4):130-134.
    [4]刘仲秋,廉照彬,章青.引水隧洞开挖释放荷载模拟方法的对比研究[J].地下空间与工程学报,2014,10(2):415-422.
    [5]杨正保.隧道掘进超前支护技术研究[D].武汉:武汉大学,2005.
    [6]陈俊涛,肖明,郑永兰.用OpenGL开发地下结构工程三维有限元图形系统[J].岩石力学与工程学报,2006,25(5):1 015-1 020.
    [7]张巍.地下工程复杂渗流场数值模拟与工程应用[D].武汉:武汉大学,2005.

© 2004-2018 中国地质图书馆版权所有 京ICP备05064691号 京公网安备11010802017129号

地址:北京市海淀区学院路29号 邮编:100083

电话:办公室:(+86 10)66554848;文献借阅、咨询服务、科技查新:66554700