石膏质岩隧道工法优选
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Excavation Method Optimization of the Gypsum Rock Tunnel
  • 作者:赵国军 ; 陈钒 ; 欧阳汛
  • 英文作者:ZHAO Guojun;CHEN Fan;OU Yangxun;Power China Road Bridge Group Co., Ltd;School of Civil and Environmental Engineering,University of Science and Technology Beijing;State Key Laboratory of Coal Mine Disaster Dynamics and Control, Chongqing University;
  • 关键词:石膏质岩 ; 开挖方法优选 ; 现场测试
  • 英文关键词:gypsum rock;;the excavation method optimization;;field test
  • 中文刊名:XBZY
  • 英文刊名:Westem Resources
  • 机构:中电建路桥集团有限公司;北京科技大学土木与环境工程学院;重庆大学煤矿灾害动力学与控制国家重点实验室;
  • 出版日期:2017-04-20 19:36
  • 出版单位:西部资源
  • 年:2017
  • 期:No.77
  • 基金:中国水电建设集团路桥工程有限公司重庆梁忠高速公路施工总承包部技术开发项目(2014-5000-10-000122)
  • 语种:中文;
  • 页:XBZY201702077
  • 页数:6
  • CN:02
  • ISSN:15-1331/P
  • 分类号:191-196
摘要
石膏质岩的膨胀特性严重影响隧道的施工设计及其后期的正常使用,目前该类岩体隧道的设计施工大都偏保守,合理的隧道工法是石膏质岩体隧道安全稳定的有力保障。以重庆梁忠高速公路礼让隧道石膏段为工程依托,采用数值模拟,进行工法优选并提出相应施工要求,得出以下结论:(1)对石膏段隧道采用全断面法开挖,支护结构受力最大,变形相对也更大,单侧壁导坑法支护受力最小,变形相对要小,但工序复杂,上下台阶法工序相对简单,变形及受力在允许范围内。(2)选取断面进行台阶法开挖现场测试,提出开挖阶段严格控制爆破及仰拱及掌子面间距,并加强各类支护,加深仰拱等相应现场要求。(3)现场测试结果显示隧道变形实测值较模拟数值稍有偏小,隧道整体偏安全,礼让隧道石膏段采用上下台阶法开挖可行。研究成果对类似石膏质岩隧道提供了有益借鉴。
        The expansion features of the gypsum rocks seriously affect the construction of the tunnel design and its normal use in the late period, the design and construction of these tunnels are mostly conservative at present, Reasonable construction methods are powerful guarantees for gypsum rock tunnels' safety and stability. As the gypsum rock section of Lirang tunnel in Chongqing, Liang Zhong highway for the project, using the numerical simulation, to optimize the construction method and put forward something requirements, the conclusions are as follows:(1)when the gypsum section tunnel excavated by the whole section method, the supporting structure is largest forced, the tunnel deformation is relatively more, the supporting force is minimal when the tunnel excavated by the CD method, deformation is relatively smaller, while the process is complicated, up and down the steps method procedure is relatively simple,also the deformation and stress in the allowed range.(2)Select some sections to have a field test with steps method, put forward that the excavation process should strictly controlled blasting and the distance between the inverted arch and constraints spacing, besides, all kinds of the support should be strengthen, also the inverted arch should be deepen and other corresponding requirement on site.(3)The field test results show that the measured values of the tunnel deformation are slightly smaller than the simulation values, the tunnel is in a good security, it is feasible of the Gypsum tunnel section excavated by steps method. Research provides useful reference for similar gypsum rock tunnel.
引文
[1]李潮雄.大别山隧道新奥法施工的围岩分级和监控量测研究[D].武汉理工大学,2009.
    [2]杨帆.浙温铁路隧道载荷特征与安全性的研究[D].山东科技大学,2015.
    [3]陈祥林.公路隧道复合支护结构与高地应力围岩相互作用分析与应用研究[D].上海交通大学,2010.
    [4]郭文明.公路超大断面隧道扁平率及施工方法优选研究[D].长安大学,2012.
    [5]郭禹呈.回头沟隧道偏压段施工方法研究[D].吉林大学,2016.
    [6]王铁男.浅埋暗挖地铁隧道开挖方案技术优化研究[D].沈阳大学,2011.
    [7]李达.长大隧道穿越断层区施工力学特征及施工优化方法研究[D].西南交通大学,2012.
    [8]范小伟,徐林生.长冲隧道进口段开挖方法的优化分析[J].重庆交通大学学报自然科学版,2008,27(2):225-227.
    [9]黄波.公路隧道软弱围岩开挖方法研究[J].土工基础,2004,18(5):59-61.
    [10]单位中交第一公路工程局有限公司.公路隧道施工技术规范[M].人民交通出版社,2009.

© 2004-2018 中国地质图书馆版权所有 京ICP备05064691号 京公网安备11010802017129号

地址:北京市海淀区学院路29号 邮编:100083

电话:办公室:(+86 10)66554848;文献借阅、咨询服务、科技查新:66554700