介绍了220kV降压变电站主接线和变压器选型等电气一次部分设计,通过对变电站短路电流的计算,分析了断电路和隔离开关的选择。
The design of the primary part of the 220 kV step-down substation and the selection of the transformer were introduced.Based on calculating the short circuit of the substation,the selection of the circuit and the isolating switch were analyzed.