为了保证煤矿井下长距离工作面准确贯通,必须制定合理的贯通测量方案,采用有效的测量方法。以黄陵二号煤矿205工作面为背景,对长距离工作面巷道贯通进行了测量设计,通过对井下导线测量与高程测量进行分析,提出了提高测量精度的可行性方法。通过对贯通测量的误差进行计算分析,检验了贯通测量方案和方法的合理性。
In order to ensure the accurate holing-through of long-distance working faces in coal mines,the reasonable holingthrough survey plan must be established and effective measurement methods should be adopted. Taking No. 205 working face in Huangling No. 2 mine as an example,the measurement design of roadway holing-through in long-distance working face was carried out. Through the analysis of underground traverse survey and elevation measurement,a feasible method to improve the measurement accuracy was proposed. By the calculation and analysis of the error of the holing-through survey,the rationality of holing-through survey plan and method was tested.
引文
[1]李兴国.大型矿井巷道贯通测量方法与误差分析[J].煤炭科学技术,2012,40(7):93-95.
[2]李正中.矿山测量学[M].徐州:中国矿业大学出版社,1988.
[3]孔素丽.黄玉川煤矿特大型贯通测量实践分析[J].煤炭科学技术,2015,43(8):149-152.
[4]王启善.特长距离高精度巷道贯通测量方案设计及精度分析[J].煤矿安全,2011,42(3):135-138.
[5]梁振华.贯通测量误差的预计及在测量中应注意的问题[J].煤炭技术,2013,32(4):128-129.
[6]彭东东.贯通测量中的误差预计及控制研究[J].矿山测量,2012,39(4):63-64.