摘要
介绍了深圳市深业上城塔1#楼巨型钢混凝土框架柱外围非标准层的单片爬模施工工艺。由于塔楼巨柱截面大、施工难度高,故在爬模爬升过程中,在水平结构楼板无法附着的情况下,采取在楼层之间增加措施钢柱,以作为组合附着式液压爬模非标准层水平结构楼板之间附着点的方法,加强了该类型爬模爬升的灵活性及实用性。
The monolithic climbing formwork construction technology for the outer non-standard floor of the giant steel reinforced concrete frame columns on the 1# building of Shenye Shangcheng Tower in Shenzhen City is introduced.Because of the large cross section and high construction difficulty of the giant column of the tower, in the climbing process of climbing formwork, when the floor of horizontal structure can not be attached, some steel columns between the floors are used to serve as the attachment point between the floors of non-standard horizontal structure for the combined attachment-type hydraulic climbing formwork, which enhances the flexibility and practicability of climbing formwork of this type.
引文
[1]成禹.高层建筑非标准层及变截面结构的爬模施工研究[J].建筑施工,2018,40(4):557-559.
[2]王鸿章,张宏军,姚富成,等.轨道附着式超高架体钢骨混凝土巨柱爬模施工技术[J].施工技术,2016,45(15):66-68.
[3]李江华,魏晨康,王强,等.武汉绿地中心立面曲变巨柱爬模施工技术[J].施工技术,2017(22):5-8.
[4]顾国明.超高层建筑滑模法与爬模法施工技术[J].建筑机械化,2009,30(11):72-76.
[5]管盈铭.扬州某高层建筑爬模施工安全管理研究[J].江苏建筑,2017(增刊1):71-72.
[6]张胜良,陆静文,黄曙亮,等.超高层建筑爬模施工测量技术在望京SOHO工程的应用[J].测绘通报,2013(增刊1):137-139.
[7]潘存珍.高层建筑爬模施工新工艺应用与推广[J].门窗,2017(6):251.