摘要
通过分析哈尔乌素露天煤矿中间搭桥施工流程,计算得到搭桥准备时间、搭桥时间以及拆桥时间。在考虑各流程之间的逻辑关系基础上,结合生产实际,得到搭桥全流程时间。最后采用甘特图对露天矿中间搭桥流程进行描述,为哈尔乌素露天煤矿今后搭桥组织管理提供可靠依据。
By analyzing the bridging construction process in Ha'erwusu Open-pit Coal Mine, the article calculates the preparation time for bridging, bridging time and demolition time. On the basis of the logical relationship between the various processes, the mine obtains full process time of the bridging by combining the production practice. In the end, the article uses Gantt chart to describe the bridging process in the open-pit mine, so as to provide a reliable basis for the management of Ha'erwusu Open-pit Coal Mine in the future.
引文
[1]刘福明,才庆祥,陈树召,等.露天煤矿中间搭桥适用条件与关键参数的确定[J].煤炭学报,2015,40(1):73-79.
[2]昌珺.露天煤矿内排期间下部水平汽车开拓运输系统优化[D].徐州:中国矿业大学,2015.
[3]胡存虎,罗怀廷.哈尔乌素露天矿下部开拓运输系统优化研究[J].中国煤炭,2014,40(S1):11-14.
[4]钮景付,杨飞,周伟,等.哈尔乌素露天矿内排期间下部开拓运输系统优化[J].金属矿山,2014(7):17-21.
[5]谷君旺,张丁.哈尔乌素露天矿斜坡道形成方法对比分析[J].露天采矿技术,2012(3):56-57+64.
[6]万蒙蒙.基于露天矿斜坡道的排土规划研究[D].徐州:中国矿业大学,2016.
[7]刘月亭.通过整体排土规划及搭桥节约运距[J].露天采矿技术,2016,31(1):52-55.
[8]周四根.特大型露天矿道路优化设计研究[J].采矿技术,2014,14(5):13-14.
[9]黄悦林,刘宇.哈尔乌素露天煤矿搭桥拆桥法的应用[J].露天采矿技术,2014(1):53-54.
[10]张云蛟.BIM时代项目进度管理之抉择:甘特图PK流线图[J].中华建设,2017(5):24-26.