基于实时风险监测技术获得核电厂当前组态的风险信息,用于实时风险管理,可以更好地反映核电厂状态,有效提高安全性和经济性水平。允许组态时间是实时组态风险管理中评价设备停役组态的一个风险指标。文中给出基于实时风险的允许组态时间的计算方法,以及在多个停役设备叠加情况下考虑已经停役设备的累积风险的贡献。
Risk information of NPP's current configuration is obtained through real-time risk monitoring technology and used in real-time risk management,which reflect the state of nuclear power plant and improve the safety and economy.Allowed Configuration Time(ACT) is a risk target which used to evaluate configuration about unavailable components in real-time configuration risk management.This paper presents the calculation method of ACT based on real-time risk.The calculation of ACT of configuration about multiple outage components considers the accumulated risk increment about equipment that remains unavailable across the configurations.
引文
[1]Nuclear Energy Institute.US Nuclear Power Plants General U.S.Nuclear Information[DB/OL].https://www.nei.org/Knowledge-Center/Nuclear-Statistics/USNuclear-Power-Plants.
[2]国家核安全局.关于发布《概率安全分析技术在核安全领域中的应用》(试行)的通知[EB/OL].2010.[2010-02-08].http://www.zhb.gov.cn/gkml/hbb/haq/201003/t20100305_186511.htm.
[3]EPRI.PSA application guide[R].Palo Alto,CA:Electric Power Research Institute,1995.