工程量清单模式的合同管理研究
详细信息    本馆镜像全文|  推荐本文 |  |   获取CNKI官网全文
摘要
工程量清单计价是国际上普遍采用的计价方式,至今已有上百年历史。我国从2003年7月1日开始全面实施清单计价以来,目前可以说是仍处于从定额计价向清单计价的过渡期,处于在工程造价管理由传统的模式向市场模式转变时期,因而与清单计价相适应的合同管理文本及配套措施均不完善。
     本文分析与清单计价相适应的合同结构,对比研究国内外清单计价下的合同文本,指出国内现有合同文本的不适应性及改进建议;研究国内外清单计价下各种招投标方法优缺点和适用范围;结合运筹学理论,提出报价的线性规划及博弈平衡两阶段优化模型,并进行例证;指出国内外合同价款调整方法的不同适应条件;对比研究国内外清单计价索赔数学模型及其使用范围;运用多属性效用函数理论,探讨工程合同谈判数学模型的利用;利用模糊数学理论,对合同评判的一种模型方法进行了验证;指出在清单计价下完善相应工程担保与工程保险制度的重要性;研究合同各方存在的风险及其风险对策。
Bill of Quantities, as a international assessing value method has been widely used for more than a few hundred years. From July 1, 2003, our country began to use this method. However, until now, we are still in a period of transferring from the conventional ration value to the Bill of Quantities and it also a transition period of traditional model to a market model. Under these conditions, a few of contract texts and management measures which are compatible with Bill of Quantities are not perfect.
     Based on analyzing contract structure of Bill of Quantities and comparing the domestic and foreign contract texts , this paper pointed out some aspects of domestic contract versions which are not adaptability to Bill of Quantities, and recommended improvement suggestion. Meanwhile, the paper studied advantages and disadvantages of the domestic and foreign bidding method of Bill of Quantities, and the scope of application. Based on operations research theory, the paper established unbalanced bid price the mathematical model and gave a example to illustrate. It pointed out different contract price adjustment conditions of domestic and international, comparatively studied domestic and international pricing claims and the use scope of mathematical models, established the project contract negotiations mathematical model by the multi -attribute utility function theory, verified a contract evaluation model by fuzzy theory. In this paper, I also pointed out the importance of project guarantee and the issuance system corresponding for Bill of Quantities, researched risk and risk measure of contract.
引文
[1]张焕,吕广.推行工程量清单计价加强建筑工程合同管理.经济师,2004第9期:267-269
    [2]何勤华,殷啸虎.中华人民共和国民法史(M).上海:复旦大学出版社.1999
    [3]宋宗宇,温长煌,曾文革.建设工程合同溯源及特点研究.重庆建筑大学学报.2003年10月第25卷第5期:87-92
    [4]杭卓珺.工程量清单计价模式下的合同管理.武汉理工大学硕士学位论文.2004
    [5]高显义.工程合同管理.同济大学出版社.2005
    [6]顾永才,田元福.招投标与合同管理科学出版社.2006
    [7]李晓龙.大型工程项目业主合同索赔管理.中国建筑工业出版社.北京.2006
    [8]杨忠直.工程监理学引论.科学出版社.北京.2004
    [9]何伯森.国际工程合同与合同管理.北京.中国建筑工业出版社1999
    [10]成虎.工程合同管理.南京.东南大学出版社.2005
    [11]梁鑑.国际工程索赔.北京.中国建筑工业出版社.1996
    [12]楼英瑞.工程量清单计价模式下施工合同风险分配条款的研究[J].工程造价管理,2004,(1):22-23.
    [13]李跃水.王延树.当前工程量清单计价中几个问题的剖析.建筑经济.2005.10总第276期:69-73
    [14]戎贤,穆静波,王大明.工程建设项目管理.北京:人民交通出版社,2006
    [15]焦杰.我国《建设工程施工合同(示范文本)》修订与完善的思考.高等建筑教育,2007.3第16卷第1期:12-15
    [16]许海,李云.《建设工程施工合同(示范文本)》与FIDIC《施工合同条件》对比分析.四川建筑科学研究.2005.4.第31卷第2期:124-127
    [17]崔忠玉.施工合同与清单计价的适应性分析.工程造价管理.2006.2:31-32
    [18]高星,成虎.推行工程量清单计价对我国现行施工合同的影响.基建优化.2004.3第25卷第3期:14-16
    [19]FIDIC.Conditions of contract for construction[M].First Edition,1999.1 80.
    [20]Emblen D.(1944).Competitive bidding for corporate securities.PhD.Dissertation,Columbia University,New York,1944.
    [21]Friedman L.(1956).A competitive-bidding strategy[J].Operations Research,Vol.4,No.1:104-112.
    [22]Friedman L.(1957).Competitive bidding strategy,PhD.Dissertation,Case Institute of Technology,Cleveland,Ohio,1957.
    [23]Hanssman F.and Rivett B.H.P.(1959).Competitive bidding[J].Operational Research Quarterly,10(1):49-55.
    [24]Casey B.J.and Shaffer L.R.(1964).An evaluation of some competitive bidding strategy models for contractors.Civil Engineering Studies.Construction Research Series No.4,University of Illinois,Urbana,Ⅲ,Jun.,1964
    [25]Gates M.(1967).Bidding strategies and probabilities[J].Journal of the Construction Division,67(1):75-107
    [26]Willenbrock J.H.(1973).Utility function determination for bidding models[J].Journal of the Construction Division,99(1):133-153.
    [27]Carr R.I.and Sandahl J.W.(1978).Bidding strategies-using multiple regressions[J].Journal of the Construction Division,104(1):15-26.
    [28]Engelbrecht-Wiggans R.(1980).Auctions and bidding models.A Survey[J].Management Science,26(2):119-142.
    [29]Carr R.I.(1982).General bidding model[J].Journal of the construction division.108(4):639-651.
    [30]Shulin Liu,K.K.Lai,Shouyang Wang.Several mathematical models for competitive bidding and auctions[J].Advances in Management Science Studies in China,Vol.1,2003.
    [31]谢炽予.经济博弈论.上海复旦大学出版社.1996年
    [32]武振.建筑产品价格形成方式研究.学位论文天津大学2004.6
    [33]白明,刘志伟.FIDIC合同条件下不平衡报价的规划模型.辽宁石油化工大学学报.2004年12月第24卷第4期:82-85
    [34]张维迎.博弈论与信息经济学,上海:上海人民出版社,上海三联书店,1996:1-15.
    [35]刘尔烈.国际工程投标报价.化学工业出版社.2006年
    [36]何伯森.国际工程承包.中国建筑工业出版社.2007年
    [37]杨平,丁晓欣等.工程合同管理.人民交通出版社.2006年
    [38]卢德林,章祥荪,马桂芝.土建工程报价优化模型.系统工程理论与实践.2002年第9期:47-53
    [39]邢军.现行建筑工程低价中标情况下博弈论在招投标中的应用.上海交通大学学报.2007年4月第41卷:45-47
    [40]李志军.FIDIC合同条件及其在我的应用实例.武汉理工大学.硕士学位论文.2005年
    [41]陈健.FIDIC合同条件土木工程合同条件在我国的应用存在的问题和对策.经济师.2003年第12期:279-280
    [42]陈蕾.论FIDIC合同条件及其应用.中国工程咨询.2003年第12期:40-43
    [43]吕炜,任玉珑,季玉华.基于一级密封的工程量清单投标价的博弈模型.管理工程学报.2007年第1期:122-126
    [44]潘介人.决策分析中的效用理论.上海:上海交通大学出版社.2000年
    [45]张莹.我国招标投标的理论与实践研究,浙江大学博士论文.2002年5月
    [46]严玲,尹贻林.工程计价学.北京.机械工业出版社.2006年
    [47]田威.FIDIC合同条件实用技巧.北京.中国建筑出版社.2002年
    [48]中华人民共和国建设部等.建设工程工程量清单计价规范(GB50500-2003).北京:中国计划出版社,2003
    [49]张宇,赵永涛,丁朝燕.工程量清单招标中业主的风险防范[J].建筑经济.2004.9:83-86.
    [50]申玲,高静.工程量清单计价模式下造价工程师责任风险分析与对策研究.南京工业大学学报:51-54
    [51]张建斌,张楠楠.我国工程风险管理与工程保险制度研究.基建优化2003年4月第24卷第2期:20-23
    [52]金德民.郑丕谔.国内外咨询(监理)工程师职业责任保险初探.天津大学学报200403
    [53]雷胜强.国际工程风险管理与保险.中国建筑工业出版社.2002
    [54]何增勤.工程项目投标策略.天津大学出版社.2004
    [55]宋吉荣,钟胜.工程量清单报价下工程项目招投标的一种新模式,软科学,2006(5):82-85。
    [56]宋吉荣.工程量清单计价下最低价中标的博弈分析.铁道建筑2006(12):93-95。
    [57]宋吉荣,钟胜.工程量清单报价下招标组织形式研究.四川建筑科学 研究,2007(1):190-193。
    [58]宋吉荣,钟胜,郭耀煌.工程量清单报价模式下招标评标模式研究,西南师范大学学报(自然科学版),2007年第32卷(2):128-131。
    [59]全国造价工程师执业资格考试培训教材编审委员会编.工程造价计价与控制.中国计划出版社.2006
    [60]姜宏,陈富坚,赵军.工程变更及其国外研究现状.桂林工学院学报.2001年4期:137-139
    [61]Clark W G.Claims avoidance and resolution[M].Trans.American Assoiation cost Engineering,Boston,Mass,1993,121
    [62]Zeitoun A A.Early warning signs of project changes[R].Construction Industry Institute,Source Document,CII,Austin,Tex,1992.24
    [63]宋宗宇,郭金虎,刘树利.建设工程合同标准文本国际实践及借鉴.重庆建筑大学学报.2001年4期:101-105