基于要素的建设项目协同管理研究
详细信息    本馆镜像全文|  推荐本文 |  |   获取CNKI官网全文
摘要

Each kind of problems which existed in the present project management are simple summarized, and the basic reason lies in various problems of project management is the essential factors lacks of effective conformity and coordination. Starting from the coordination essence obtained in the human society, the intrinsic demand to synergic management in the construction management is analyzed. After analyzing the project coordination in the cooperation management, partnering model, the synergic degree of all different construction patterns are analyzed separately.
     Firstly, the grey forecast and optimal decision-making on the total life cost of construction project is build, and the whole life cycle time, quality and cost goal of the construction project is resolved. According to the basic thought of the project integration, all materials, information and data in all different phases needs to be integrated. And a new method that applies the grey forecast approach to the cost prediction and the time optimization is proposed in this paper. Through analyzing the relationship of time, quality and cost, the reasonable area among these three major goals of the project is determined qualitatively. Recurring to the network planning technology, its object function and restrictions are explained carefully to obtain the most satisfied decision scheme and to control goals in the project management.
     Secondly, the SIPOC model of the construction project integration is proposed, and the organization structure to support this model is designed. Learning from the basic thought of the SCM, the Suppliers—Input—Process—Output—Customers (SIPOC) model of the construction project integration is proposed, and how to carrying on SIPOC model within the inter-construction project is discussed deeply. The dynamic united organization is established, which composed by construction participants and undertakes corresponding responsibility. The seamless link between different procedures of construction project is supported through the dynamic adjust. Based on the reality of construction project, the key-leading group of the dynamic united organization is analyzed. Finally, the application and benefits of this model is illuminated combined the development practice of one Shenzhen Building.
     Thirdly, the information asymmetry existed in construction project is analyzed, and the information sharing mechanism and realization methods are put forward. After the two layers principal-agent relationship among the owner, contractor and supervisor in the building phase of construction project is analyzed, the game model among the owner, contractor and supervisor is established. Through designing the rational management contract, utilizing the believable punishment threaten the contractor and supervisor, the contractor and supervisor can be impelled to work hard and reduce its possibility of conspired. The information integration model of construction project is established from the stage information integration and the participant integration. And the realization of the information integration model is designed from the selection of network structure, the planning of system application layer, the designing of database, etc. After the information processing procedure model of the information integration system is explained, every functional management integrated method of the construction project is suggested.
     Lastly, the synergic analysis model under and between the construction time, process and infarction is set up. The construction project management goal contains the expense, the quality, the security, the environmental protection and so on, these project goals realizations need to integrate and coordination all essential factors involved in the construct management, especially the time, the flow and the information factor. It needs to uses the quantitative analysis and the qualitative analysis, in the concrete analysis time, the flow and in the information essential factor integration foundation, to realizes the best control in the project expense, quality, security, environmental protection through the time, process and information synergic. While analyzes the various essential internal coordination of each factors and the external coordination between these factors and the market environment quantitatively, the concrete plan is provided to realizes the construction goals synthesis optimization.
引文
[1] Project Management Institute Standards Committee. A Guide to the Project Management Body of Knowledge Upper Darby [M]. PA:Project Management Institute,1996
    [2] 凯西·施瓦尔贝. IT 项目管理[M]. 北京:机械工业出版社,2002
    [3] Shamil G. Naoum, David Langford. Management contracting – the client’s view [J]. Journal of Construction Engineering and Management, 1987, 113(3): 369-384
    [4] Issaka Ndekugri, Adrian Turner. Building procurement by design and build approach [J]. Journal of Construction Engineering and Management, 1994, 120(2): 243-256
    [5] David C. Brown, Melanie J. Ashleigh, Michael J. Riley. New project procurement process [J]. Journal of Management in Engineering, 2001, 17(4): 192-201
    [6] Shing-Tao Chang. Reasons for cost and schedule increase for engineering design projects [J]. Journal of Management in Engineering, 2002, 18(1): 29-36
    [7] Douglas D. Gransberg, William D. Dillon, Lee Reynolds, Jack Boyd. Quantitative analysis of partnered project performance [J]. Journal of Construction Engineering and Management, 1999, 125(3): 161-166
    [8] Feniosky Pena-Mora, Tadatsugu Tamaki. Effect of delivery systems on collaborative negotiations for large-scale infrastructure projects [J]. Journal of Management in Engineering, 2001, 17(2): 105-121
    [9] Min-Yuan Cheng, Cheng-Wei Su, Horng-Yuh You. Optimal project organizational structure for construction management [J]. Journal of Construction Engineering and Management, 2003, 129(1): 70-79
    [10] J. Rodney Turner, Stephen J. Simister. Project contract management and a theory of organization [J]. International Journal of Project Management, 2001, 19: 457-464
    [11] Eddie W. L. Cheng, Heng Li. Construction partnering process and associated critical success factors: quantitative investigation [J]. Journal of Management in Engineering, 2002, 18(4): 194-203
    [12] Griffith A. F., Gibson Jr. G. E. Alignment during preproject planning [J]. Journal of Management in Engineering, 2001, 17(2): 69-76
    [13] Cynthia M. Ruff, David A. Dzombak, Chris T. Hendrickson. Owner-Contractor relationship on contaminated site remediation projects [J]. Journal of Construction Engineering and Management, 1996, 122(4): 348-354
    [14] Jimmie Hinze, Andrew Tracey. The contractor-subcontractor relationship: the subcontractor’s view [J]. Journal of Construction Engineering and Management, 1994,120(2): 274-287
    [15] Michael S. Puddicombe. Designers and contractors: impediments to integration [J]. Journal of Construction Engineering and Management, 1997, 123(3): 245-252
    [16] William J. Rasdorf, Osama Y. Abudayyeh. Cost- and schedule-control integration: issues and needs [J]. Journal of Construction Engineering and Management, 1991, 117(3): 486-502
    [17] A.J.G. Babu, Nalina Suresh. Project management with time, cost and quality consideration [J]. European Journal of Operational Research, 1996, 88: 320-327
    [18] Do Ba Khang, Yin Mon Myint. Time, cost and quality trade-off in project management: a case study [J]. International Journal of Project Management, 1999, 17(4): 249-256
    [19] PED Love, A. Gunasekaran, H. Li. Concurrent engineering: a strategy for procuring construction projects [J]. International Journal of Project Management, 1998,16(6): 375-383
    [20] Neil N. Eldin. Concurrent engineering: a schedule reduction tool [J]. Journal of Construction Engineering and Management, 1997, 123(3): 354-362
    [21] A. Jaafari. Concurrent Construction and life cycle project management [J]. Journal of Construction Engineering and Management, 1997, 123(4): 427-436
    [22] David C. Brown, Melanie J. Ashleigh, Michael J. Riley. New project procurement process [J]. Journal of Management in Engineering, 2001, 17(4): 192-201
    [23] William W. Badger, Donald E. Mulligan. Rationale and benefits associated with international alliances [J]. Journal of Construction Engineering and Management, 1995,121(1): 100-111
    [24] David N. Sillars, Roozbeh Kangari. Japanese construction alliance [J]. Journal of Construction Engineering and Management, 1997, 123(2): 146-152
    [25] Feniosky Pena-Mora, Chun-Yi Wang. Computer-supported collaborative negotiationmethodology [J]. Journal of Computing in Civil Engineering, 1998, 12(2): 64~81
    [26] Stephen R. Thomas, Richard L. Tucker, William R. Kelly. Critical communications variables [J]. Journal of Construction Engineering and Management, 1998, 124(1): 58-66
    [27] Sai-On Cheung, Henry C. H. Suen, Tsun-lp Lam. Fundamentals of alternative dispute resolution processes in construction [J]. Journal of Construction Engineering and Management, 2002, 128(5): 409-417
    [28] Victor E. Sanvido, Deborah J. Medeiros. Applying computer-integrated manufacturing concepts to construction [J]. Journal of Construction Engineering and Management, 1990, 116(2): 365-379
    [29] Gijsbertus T. “Bart” Luiten, Frits P. Tolman. Automating communication in civil engineering [J]. Journal of Construction Engineering and Management, 1997, 123(2): 113-120
    [30] Heloisa Martins Shib, Mitchell M Tseng. Workflow technology-based monitoring and control for business process and project management [J]. International Journal of Project Management, 1996, 14(6): 373-378
    [31] F. Pena-Mora, K. Hussein, S. Vadhavkar, K. Benjamin. CAIRO: a concurrent engineering meeting environment for virtual design teams [J]. Artificial Intelligence in Engineering, 2000, 14(3): 203-219
    [32] C. J. Anumba, A. K. Duke. Telepresence in concurrent lifecycle design and construction [J]. Artificial Intelligence in Engineering, 2000, 14(3): 221-232
    [33] Feniosky Pena-Mora, Gyanesh Hari Dwivedi. Multiple device collaborative and real time analysis system for project management in civil engineering [J]. Journal of Computing in Civil Engineering, 2002, 16(1): 23-38
    [34] O’Brien W J, London K,Vrijhoef R. Construction Supply Chain Modeling:a Research Review and Interdisciplinary Research Agenda [C],Proceedings IGLC . GramadoZ:Brazil,1-19
    [35] R. Barker, S. Hong-Minh, M.M. Naim.The terrain scanning methodology. Assessing and improving construction supply chains [J]. European Journal of Purchasing & Supply Management,2000,6:179-193
    [36] J. Rodney Turnera, Ralf Muller. On the nature of the project as a temporary organization [J]. International Journal of Project Management,2003,21: 1–8
    [37] 史美林, 向勇, 杨光信. 计算机支持的协同工作理论与应用[M]. 北京:电子工业出版社,2000
    [38] Feniosky Pena-Mora, Chun-Yi Wang. Computer-supported collaborative negotiation methodology [J]. Journal of Computing in Civil Engineering, 1998, 12(2): 64-81
    [39] 张金锁, 李立, 贾凤锁. 建设项目管理学[M]. 北京:科学出版社,2000
    [40] 刘尹生, 任宏, 牛永宁等. 工程造价管理基础理论与相关法规[M]. 北京:中国计划出版社,2003
    [41] Walid Belassi, Oya Icmeli Tukel. A new framework for determining critical success/failure factors in projects [J]. International Journal of Project Management, 1996, 14(3): 141-151
    [42] A.J.G. Babu, Nalina Suresh. Project management with time, cost and quality consideration [J]. European Journal of Operational Research, 1996, 88: 320-327
    [43] Do Ba Khang, Yin Mon Myint. Time, cost and quality trade-off in project management: a case study [J]. International Journal of Project Management, 1999, 17(4): 249-256
    [44] Brian Helbrough. Computer assisted collaboration – the fourth dimension of project management? [J]. International Journal of Project Management, 1995, 13(5): 329-333
    [45] Moore C J. Collaborative and concurrent engineering in the construction industry [J]. Artificial Intelligence in Engineering, 2000, 14(3): 201-202
    [46] David C. Brown, Melanie J. Ashleigh, Michael J. Riley. New project procurement process [J]. Journal of Management in Engineering, 2001, 17(4): 192~201
    [47] 何清华, 陈发标. 建设项目全寿命周期集成化管理模式的研究 [J]. 重庆建筑大学学报, 2001, 23(4): 75-80
    [48] Ahmed, Nazim U. A design and implementation model for life cycle cost management system [J]. Information & Management, 1995, 28(4): 261-269
    [49] Neale C.W., Wagstaff G. Discounted Cash Flow and Life Cycle Costing for Construction Projects [J]. International Journal of Operations & ProductionManagement, 1985, 5(4): 55-70
    [50] Douglas D.G., Michael A.E. Life cycle project management [J]. AACE International Transactions. Morgantown: 1997: 288-292
    [51] David G.W. Life cycle costing----theory, information acquisition and application [J]. International Journal of Project Management, 1997, 15(6): 335-344
    [52] Sadi A.A., Abdulmohsen A.H., Osama A.J., et al. Assessment of the problems of application of life cycle costing in construction projects [J]. Cost Engineering, Morgantown, 2002, 44(2): 17-22
    [53] Sarfraz A.M., Christine X.D. Decision-making over the project life cycle: An analytical hierarchy approach [J]. Project Management Journal, 1999, 30(1): 40-52
    [54] Timothy J.K., Joseph A.P. Leadership in project life cycle and team character development [J]. Project Management Journal: 1999, 30(2): 8-13.
    [55] Durairaj, Senthil Kumaran, etc. Evaluation of Life Cycle Cost Analysis Methodologies [J]. Corporate Environmental Strateg, 2002(1), 9(1): 30-39
    [56] Kamara, John M., etc. Assessing the suitability of current briefing practices in construction within a concurrent engineering framework [J]. International Journal of Project Management, 2001, 19(6): 337-351
    [57] Jaafari, Ali, Manivong, Kitsana. The need for life-cycle integration of project processes [J]. Engineering Construction & Architectural Management, 1999, 6(3): 235-255
    [58] Jaafari, Ali. Life-cycle project management: a proposed theoretical model for development and implementation of capital project [J].Project Management Journal, 2000, 31(1): 44-53
    [59] Khalfan Malik M.A., Anumba Chimay J., Siemieniuch Carys E., etc. Readiness Assessment of the construction supply chain for concurrent engineering [J]. European Journal of Purchasing & Supply Management, 2001, 7(2): 141-153
    [60] Leonard D.A, Guillermo F.S. Project-based course for integration of design and construction at WPI [J]. Journal of Professional issues in Engineering Education and Practice, 1998(10), 124(4), 97-104
    [61] Bowersox D.J., Closs D.J., Copper M.B. Supply chain logistics management [M].Beijing:China Machine Press,2002
    [62] Stevens G.C. Integrating the Supply Chain [J]. International Journal of Physical Distribution & Material Management, 1989, 19(8): 3-8.
    [63] Cooper M.C, Ellram L.M. Characteristics of supply chain management and the implications for purchasing and logistics strategy [J]. International Journal of Logistics Management, 1993,4(2): 13-24
    [64] Egan J.S. Rethinking Construction. Construction Task Force report [R]. Department of the Environment, Transport and the Regions, London, 1998
    [65] Dainty A, Briscoe G.H, Millet S. New perspectives on construction supply chain integration [J]. Supply Chain Management: An International Journal, 2001,6(4): 163-173
    [66] Pearson A. Chain reaction. Building [N], 1999,12 March, 54-55
    [67] Wong A, Kanji G.K. Quality culture in the construction industry [J]. Total Quality Management, 1998, 9(4-5): 133-140
    [68] Love P.E.D. Construction supply chains [J]. European Journal of Purchasing and Supply Management, 2000, 6(3-4): 145-147
    [69] Lamming R. Squaring the lean supply with supply chain management [J]. International Journal of Operations & Production Management, 1996,16(2): 183-196
    [70] Barker R. Hong-Minh S. Naim M.M. The terrain scanning methodology: assessing and improving construction supply chains [J]. European Journal of Purchasing and Supply Management, 2000,6(3-4): 179-19
    [71] Peter E.D.Love, Zahir Irani, David J. Edwards. A seamless supply chain management model for construction [J]. Supply Chain Management: An International Journal, 2004, ((1): 42-56
    [72] 张维迎. 博弈论与信息经济学 [M]. 上海:上海人民出版社, 1996
    [73] Lampel Joseph, Miller Roger, Floricel Serghei. Information asymmetries and technological innovation in large engineering construction projects [J]. R & D Management, 1996, 26(4): 357-369
    [74] 张德群, 关柯. 建筑业信息模型及信息不对称分析 [J]. 哈尔滨建筑大学学报, 2000, 33(4): 93-95
    [75] 陈渤. 信息不对称与建设项目管理—从2001年诺贝尔经济学奖谈起 [J]. 中国投资, 2001(12): 78-79
    [76] 张天森, 李元生. 建筑市场信息不对称研究 [J]. 建筑经济,2002(9):11-13
    [77] Caswill Chris. Principals, agents and contracts [J]. Science & Public Policy, 2003, 30(5): 337-346
    [78] Keser Claudia, Willinger Marc. Principals’ principles when agents’ actions are hidden [J]. International Journal of Industrial Organization, 2000,18(1): 163-185
    [79] 徐鼎. 项目建设期道德风险的博弈分析研究 [J]. 中国软科学, 1999(2): 81-84
    [80] J Rodney Turner, Ralf Muller. Communication and co-operation on projects between the project owner as principal and the project manager as agent [J]. European Management Journal, 2004, 22(3): 327
    [81] Peterson Steven P. Some experimental evidence on the efficiency of dividend signaling in resolving information asymmetries [J]. Journal of Economic Behavior & Organization, 1996, 29(3): 373-388
    [82] David Jaggar, Andrew Ross, Peter E.D. Love, etc. Overcoming information opacity in construction: a commentary [J]. Logistics Information Management, 2001, 14(5-6): 413-421
    [83] L. Jawahar Nesan. Efficacy-information for implementing learning in construction [J]. The Learning Organization, 2004, 11(1): 45-66
    [84] McCabe Mark J. Principals, agents, and the learning curve: The case of steam-electric power plant design and construction [J]. The Journal of Industrial Economics, 1996, 44(4): 357-375
    [85] Sung Jaeyoung. Linearity with project selection and controllable diffusion rate in continuous-time principal-agent problems [J]. The Rand Journal of Economics, 1995, 26(4): 720-743
    [86] 成力为. 建设主体寻租活动的成本收益分析 [J]. 哈尔滨建筑工业大学学报, 2001, 34(1): 110-113
    [87] 王艳, 黄学军, 王浣尘. 工程质量监控的博弈分析[J]. 中国软科学, 2003(5): 138-141
    [88] 秦旋. 工程监理制度下的委托代理博弈分析 [J]. 中国软科学, 2004(4): 142-146
    [89] Brent James C. An Agent and Two Principals [J]. American Politics Quarterly, 1999, 27 (2): 236-260
    [90] 郭建鸾. 创业投资信息不对称的博弈分析 [J]. 华侨大学学报(哲学社会科学版), 2004(2): 15-21
    [91] 蒋海, 刘少波. 信息结构与金融监管激励:理论与政策含义 [J]. 财经研究,2004, 30(7): 26-34
    [92] Jaafari, Ali. Life-cycle project management: a proposed theoretical model for development and implementation of capital project [J]. Project management Journal, 2000, 31(1): 44-53
    [93] 李蔚. 建设项目的供应链集成管理研究[J]. 基建优化,2005,26(1):16-19
    [94] 马士华等著. 供应链管理 [M]. 北京:机械工业出版社,2000
    [95] 何清华, 芦勇, 陈发标. 全寿命周期集成化管理信息系统(LMIS)开发总体方案[J]. 基建优化, 2001, 22(1): 13-15
    [96] 宋志航. 建设项目管理集成信息系统的研究 [D]. 上海:同济大学, 2002
    [97] Chen Yuhong, Liu Jun. Using grey theory estimates cost of unmanned plane’s repairing [J]. Journal of Beijing University of Aeronautics and Astronautics, 2004, 30(3): 214-216
    [98] Rowene J R. Evaluation of hazardous material life cycle cost tools for use in air force hazardous material pharmacies [D]. US: Air Force Institute of Technology air University, 1997
    [99] Deng Julong. Element on Grey Theory [M]. Wuhan: HUST Press, 2002
    [100] Scott C N. Guidelines for using economic factors and maintenance costs in life cycle cost analysis [R]. PB982110638, 1997
    [101] Gu Xiaohui, Wang Xiaoming, Zhao Youshou. Research on estimation model of ammunition and rocket system development cost based on the grey system [J]. Journal of Nanjing University of Science and Technology, 2001, 25(2): 117-120
    [102] Guo Jizhou, Song Guibao, Peng Shaoxiong. Analysis for operational and support cost of equipment using grey model [J]. Systems Engineering and Electronics, 2004, 26(1): 64-67
    [103] Oberlender, G.D, Trost, S. M. Predicting accuracy of early cost of early costestimates based on estimate quality [J]. Journal of Construction Engineering & Management, 2004, 127(3): 173-182
    [104] LI Wei,CAI Shu-qing. The dialectical relationship of time-cost-quality in whole life cycle construction project management[A],2004 International Conference on Construction & Real Estate Management[C]. Hongkong: P.R.China, 267-270
    [105] Abdelkader Yousry H. Evaluating project completion times when activity times are Weibull distributed [J]. European Journal of Operational Research,2004, 157(3):704-715
    [106] 李蔚,蔡淑琴. 建设项目全寿命成本的预测模型与优化决策研究[J]. 建筑技术开发,2006,33(2): 待发
    [107] McKim R, Hegazy T. Attalla M. Project performance control in reconstruction projects [J]. Journal of Construction Engineering and Management , 2000 , 126 (2) : 137-141
    [108] Rwelamila P D, et al. Total systems intervention: An integrated approach to time, cost and quality management [J]. Construction Management and Economics , 1995 , 13 : 235-241
    [109] 唐殿峰,秦桂娟. 工程项目质量工期费用控制模拟系统[J].沈阳建筑工程学院学报, 1998 , 14 (2) : 158-161
    [110] Babu A J G, Suresh N. Project management with time, cost, and quality considerations [J]. European Journal of Operational Research, 1996, 88 (2): 320-327.
    [111] Do Ba Khang, Yin Mon Myint. Time, cost and quality trade-off in project management: A case study [J]. International Journal of Project Management , 1999 , 17 (4) : 249-256
    [112] 王健,刘尔烈,骆刚. 工程项目管理中工期—成本—质量综合均衡优化. 系统工程学报,2004(4),19(2):148-153
    [113] Anderson D K, Tony M. Project Management Strategy—project management represented as a process based set of management domains and the consequences for project management strategy [J]. International Journal of Project Management ,2003, 21(6): 387-393
    [114] 李蔚,蔡淑琴. 建设项目集成的SIPOC模式及其组织支持[J]. 科研管理,2006,27(1):138-145
    [115] Barker R., Hong-Minh S., Naim M.M. The terrain scanning methodology. Assessing and improving construction supply chains [J]. European Journal of Purchasing & Supply Management, 2000, 6(3-4): 179-193
    [116] Harris, F. McCaffer, R. Modern Construction Management (5th ed.) [M]. Oxford : Blackwell Science, 2001
    [117] Jaafari, Ali, Manivong, Kitsana. The need for life-cycle integration of project processes [J]. Engineering Construction & Architectural Management, 1999, 6(3): 235-255
    [118] 刘尔烈, 蔡耿谦. 工程项目集成化管理 [J]. 港工技术, 2001(12): 19-21
    [119] Andrew R J Dainty, Geoffrey H Briscoe, Sarah J Millett. New perspectives on construction supply chain integration [J]. Supply Chain Management, 2001, 6(3/4): 163-173
    [120] 成虎, 陆彦. 论工程项目组织的使命 [J]. 建筑经济, 2004(9): 23-26
    [121] 常陆军, 常军波. 工程项目管理的组织形式探讨 [J]. 建设监理, 2004(5): 21-23
    [122] 虞泽, 江新, 严濛濛. 工程项目管理的组织结构优化问题研究[J]. 建筑技术开发, 2004, 31(11): 77-79
    [123] 林鸣, 马士华. 动态联盟项目管理新模式 [M] . 北京: 电子工业出版社, 2003
    [124] 彭勇. 工程建设项目的虚拟组织 [J]. 基建优化, 2003, 24(5): 5-8
    [125] 陈江红, 苏振民. 工程项目管理虚拟组织的构建及运行 [J]. 基建优化, 2003, 24(6): 3-7
    [126] Barlow, J., Jashapara, A. Organisational learning and inter-firm partnering in the construction sector [J]. The Learning Organisation, 1998, 5(2): 86-98
    [127] 李蔚. 建设项目集成的组织设计与管理[J]. 华中科技大学学报(城市科学版),2005,22(2):78-82
    [128] Hyv??ri Irja. Project management effectiveness in project-oriented business organizations [J]. International Journal of Project Managemen, 2006, 24(3):216-225
    [129] Jos P. van Leeuwen, Aant van der Zee. Distributed object models for collaboration in the construction industry [J]. Automation in Construction, 2005, 14(4): 491–499
    [130] Jaafari A.,Manivong K. The need for life-cycle integration of project processes [J]. Engineering Construction & Architectural Management, 1999, 6(3): 235-255
    [131] Aouad G., Sun M. Information modelling and integration in the construction industry: a novel approach [J]. Structural Survey, 1999, 17(2): 82-88
    [132] 马智亮, 伍炜煜, 彭明. 实现建设领域信息化之路 [M]. 北京: 中国建筑工业出版社, 2002
    [133] 成虎. 建设项目全寿命周期集成管理研究 [D]. 黑龙江: 哈尔滨工业大学, 2001
    [134] Tam C M. Use of the Internet to enhance construction communication: Total Information Transfer System [J]. International Journal of Project Management, 1999, 17(2): 107-111
    [135] 王守清. 计算机辅助建筑工程项目管理 [M]. 北京: 清华大学出版社, 1996
    [136] Ahmad Rafi, Khairul Anuar, Abdul Samad, etc. Improving spatial ability using a Web-based Virtual Environment (WbVE) [J]. Automation in Construction, 2005, 14(6): 707-715
    [137] Ma zhiliang, Wu Jianfeng. Development of management information systems for construction project based on Web [A]. Proceeding of international conference on engineering and technological sciences 2000, civil engineering in the 21st century [C]. Beijing: Science Press, 2000: 702-711
    [138] Love Peter E D, Zahir Irani. A project management quality cost information system for the construction industry [J]. Information and Management, 2003, 40(7): 649-661
    [139] 李蔚. 建设项目的信息集成模式与实现机制研究[J]. 施工技术,2005,34(12):25-27,37
    [140] 李蔚,刘小群. 工程项目集成管理及其软件系统[J]. 建筑经济,2004,(8):34-36
    [141] W. Ronald Hudson, Ralph Haas, Waheed Uddin. Infrastructure management:integrating design, construction, maintenance, rehabilitation, and renovation [M]. New York: McGraw-Hill, 1997
    [142] 成虎. 工程项目管理[M]. 北京:中国建筑工业出版社,2001.
    [143] Abul Hassan H S. A framework for applying concurrent engineering principles to the construction industry[D]. Pennsylvania:Pennsylvania State University,2001.
    [144] 仇元福, 潘旭伟, 顾新建. 项目管理中的知识集成方法和系统[J]. 科学学与科学技术管理, 2002, (8): 36-39
    [145] Seufert A., Krogh G., Bach A. Towards knowledge networking [J]. Journal of knowledge management, 1999,3(3): 180-190
    [146] Uit Beijerse R.P. Knowledge management in small and medium-sized companies: knowledge management for entrepreneurs [J]. Journal of knowledge management, 2000,4(2):162-179.
    [147] 顾基发. 物理—事理—人理(WSR)系统方法论[J]. 交通运输系统工程与信息,1995, 1(3):25-28.
    [148] 陶庆, 王威. 决策支持系统的模糊综合评价[J]. 数学的实践与认识,2005,35(5):71-79.
    [149] Jurge Bode. Decision Support with Neural Networks in the Management of Research and Development: Concepts and Application to Cost [J] . Information & Management, 1998, 134: 33 - 40.
    [150] 张玲玲,佟仁城. 企业信息系统项目综合评价指标体系探究[J] . 中国管理科学,2004,12(1): 95-100.
    [151] 陈雷等. 基于熵权系数与TOPSIS集成评价决策方法的研究[J] . 控制与决策,2003,18(4): 456-459
    [152] Davey-Wilson I.E.G. Fuzzy set adaptation for foundation construction [J]. Advances in Engineering Software, 2001, 32(10): 813-820
    [153] 郭东强. 利用熵权系数法评价企业信息化建设项目[J] . 运筹与管理,2003,12(3):76-79
    [154] 杜纲, 岳松涛. 房地产开发投资决策的熵权系数优化模型[J]. 数理统计与管理, 1999, 18 (1) : 45-49.
    [155] Evangelos Triantaphyllou. Multi-criteria Decision Making Methods: A Comp arative Study [M]. Dordrecht: Kluwer Academic Publishers, 2000. 18-22.
    [156] Cox R F. Management’s Perception of Key Performance Indicators for Construction [J]. Journal of Construction Engineering and Management , 2003 , 129(2) :142~151.
    [157] 胡永宏, 贺思辉. 综合评价方法[M] . 北京:科学出版社,2000.
    [158] Forsund F R, Hjalmarsson L. Calculating Scale Elasticity in DEA Models [J]. Journal of the Operational Research Society ,2004 ,55 :1023~1038.
    [159] Cheung SO, Ng TST, Lam KC and Sin WS, A fuzzy sets model for construction dispute evaluation [A]. Construction Innovations - Information, Process and Management [C]. London, UK, Arnold, 2001, 1(3): 117–127
    [160] Yeng-Horng Perng; Sung-Lin Hsueh; Min-Ren Yan. Evaluation of Housing Construction Strategies in China Using Fuzzy-Loic System [J]. International Journal of Strategic Property Management; 2005; 9(4): 215-232
    [161] 冯为民, 任宏, 曲成平等. 建设项目综合评价体系及模型研究[J]. 重庆建筑大学学报,2004,26(6):103-107,111
    [162] 朱传耿. 论可持续发展的五大关系[J] . 地域研究与开发,1998 ,17 (3):4-8
    [163] 千住镇雄. 经济性工学应用[M]. 郑友敬(译). 北京:经济管理出版社,1995

© 2004-2018 中国地质图书馆版权所有 京ICP备05064691号 京公网安备11010802017129号

地址:北京市海淀区学院路29号 邮编:100083

电话:办公室:(+86 10)66554848;文献借阅、咨询服务、科技查新:66554700