摘要
杨房沟水电站是我国首个采用设计施工总承包模式进行建设的百万千瓦级大型水电站,地下厂房施工是工程建设的两大主线之一。针对其花岗闪长岩的特性,采取了地质跟进、动态进行设计施工的方式,确保了工程和开挖施工安全,并提前半年完成了地下厂房开挖的目标,为混凝土转序奠定了坚实的基础。
Yangfanggou Hydroelectric Power Station is the first mega-kilowatt hydroelectric power station in China to be constructed by the general contracting mode of design and construction. The construction of underground powerhouse is one of the two main lines of construction. In view of the characteristics of its granodiorite,the way of geological follow-up and dynamic design and construction is adopted to ensure the safety of engineering and excavation construction,and the excavation goal of underground powerhouse is completed half a year ahead of schedule,which lays a solid foundation for concrete sequencing.
引文
[1]于兵.长河坝水电站地下厂房开挖施工技术实践[J].水电站设计,2019,35(1):53-56.
[2]李俊,魏宝龙,焦凯,等.大型地下洞室群开挖支护施工技术研究与实践——以杨房沟水电站为例[J].人民长江,2018,49(24):76-82.
[3]李才平,王新龙.红卫桥水电站地下厂房开挖与支护施工技术[J].黑龙江水利科技,2018,46(11):162-164,212.
[4]齐界夷,贺明武,唐昭醒,等.乌东德水电站左岸地下厂房快速安全开挖支护施工技术[J].施工技术,2018,47(7):132-135.
[5]卢春亭.大跨度拱形结构高空移动模架在水电站地下厂房顶拱施工中的应用[J].施工技术,2017,46(14):45-48.
[6]廖军,韦雨,陈军.白鹤滩左岸地下厂房顶拱对穿锚索施工技术研究[J].施工技术,2017,46(2):92-97.