摘要
针对电气化铁路无衬砌隧道存在的落石掉块病害,研究采用高强、绝缘、耐腐、阻燃的芳纶防护网进行加固的技术措施。以丰沙(丰台—沙城)线8号隧道为依托,介绍了该隧道无衬砌段病害情况,分析了采取的整治措施及尚待解决的问题。提出使用芳纶防护网进行加固,通过试验分析验证了芳纶防护网的物理性能,并阐述了隧道加固施工工艺。
In view of the falling block defect existing in the unlined tunnel of electrif ied railway,the reinforcement measures using high strength,insulation,corrosion resistance and f lame retardant aramid protective network were studied.Taking No.8 tunnel on the Fengtai-Shacheng railway as an object,the defects of unlined section in this tunnel were introduced.The reinforcement measures and unsolved problems were analyzed.It was proposed that the aramid protective network should be used to reinforcing the surrounding rock.The physical properties of the aramid protective network were verif ied through experiment and the construction technologies of tunnel reinforcement were described.
引文
[1]铁道部第三勘测设计院.铁路工程地质实例(东北、华北地区分册)[M].北京:中国铁道出版社,1996.
[2]胡厚田.崩塌与落石[M].北京:中国铁道出版社,1989.
[3]邢建鑫,申文军,韦韬,等.引导型防护网在山体危石整治中的应用[J].铁道建筑,2012,52(7):93-96.
[4]高鹤江,刘修炜.铁路桥隧病害检查观测方法[M].北京:中国铁道出版社,1987.
[5]中华人民共和国铁道部.铁路沿线斜坡柔性安全防护网:TB/T 3089—2004[S].北京:中国铁道出版社,2004.
[6]中华人民共和国交通部.公路边坡柔性防护系统构件:JT/T528—2004[S].北京:交通部公路科学研究所出版社,2004.