和畅洲左汊口门潜坝加固现场试验研究
详细信息    查看全文 | 推荐本文 |
  • 英文篇名:Field Test on the Strengthening Work of Submerged Dike at Hechangzhou Left Braided Channel
  • 作者:范兵 ; 林木松 ; 钱圣
  • 英文作者:FAN Bing;LIN Mu-song;QIAN Sheng;Water Conservancy and Agricultural Machinery Bureau of Jiangyin City;River Department,Yangtze River Scientific Research Institute;
  • 关键词:长江镇扬 ; 和畅洲汊道 ; 潜坝 ; 施工定位 ; 深水抛石 ; 尼龙网兜漂距 ; 石块漂距
  • 英文关键词:Zhenjiang-Yangzhou reach of Yangtze River;;Hechangzhou braided channel;;submerged dike;;construction positioning;;deepwater riprap;;nylon riprap's drift distance;;stone drift distance
  • 中文刊名:CJKB
  • 英文刊名:Journal of Yangtze River Scientific Research Institute
  • 机构:江阴市水利农机局;长江科学院河流研究所;
  • 出版日期:2015-09-15
  • 出版单位:长江科学院院报
  • 年:2015
  • 期:v.32;No.203
  • 语种:中文;
  • 页:CJKB201509011
  • 页数:6
  • CN:09
  • ISSN:42-1171/TV
  • 分类号:51-55+79
摘要
长江镇扬和畅洲左汊口门潜坝加固工程包括坝顶的尼龙网石兜和坡面的块石防护工程2部分。由于水下潜坝加固的设计工程量补偿系数及施工方法没有相关的规程规范和经验可借鉴,因此,为研究尼龙网石兜及块石抛投施工定位方法,确定抛石与抛投尼龙网石兜的设计工程量补偿系数,开展了现场抛投尼龙网石兜与抛石试验研究。根据现场试验结果,计算分析确定了坝顶及坝肩抛尼龙网石兜设计工程量补偿系数为1.2,水下坝坡面抛石设计工程量补偿系数为1.5;并结合理论分析,推导了尼龙网石兜漂距及石块漂距的计算公式,由试验数据反算出了尼龙石兜和块石的阻力系数。该研究成果已运用于长江镇扬和畅洲左汊口门潜坝加固工程的设计和施工中,达到了预期目的。
        The strengthening work of submerged dike at Hechangzhou left braded channel consists of two parts: rock riprap( with nylon cage) on the dike crest and slope protection by rock blocks. Since there is no related specification or experience in determining the compensation coefficient of engineering quantity and construction technique,field tests were conducted for the construction positioning,the detailed technique of rock riprap( with nylon cage),and the compensation coefficient of engineering quantity. Through the field tests,construction positioning was determined,and according to the test results,the compensation coefficient of engineering quantity of riprap at dam crest and dam abutment is 1. 2,the compensation coefficient of engineering quantity at underground dam slope is 1.5. Moreover,the calculation formula of the riprap's and nylon riprap's drift distance were derived,and in association with the field test,the riprap's and nylon riprap's drag coefficient was calculated. The research achievements have been applied to the design and construction of strengthening work of submerged dike at Hechangzhou left braded channel,and achieved expected results.
引文
[1]林木松,卢金友,张岱峰,等.长江镇扬和畅洲汊道演变和治理工程[J].长江科学院院报,2006,23(5):10-13.(LIN Mu-song,LU Jin-you,ZHANG Dai-feng,et al.Evolution and regulation works at Hechangzhou braided channel in Z-Y Reach of Yangtze River[J].Journal of Yangte River Scientific Research Institute,2006,23(5):10-13.(in Chinese))
    [2]林木松,杨光荣.长江中下游干流河道管理规划若干问题探讨[J].人民长江,2013,44(10):56-58.(LIN Mu-song,YANG Guang-rong.Discussion on Some Problems in River Channel Management Planning of Main Strem of Mid-lower Yangtze River[J].Yangtze River,2013,44(10):56-58.(in Chinese))
    [3]刘小斌,林木松.长江下游镇扬河道演变及整治研究[J].长江科学院院报,2011,28(11):1-9.(LIU Xiao-bin,LIN Mu-song.Channel Evolution and Regulation of Zhenjiang·Yangzhou Reach of the Lower Yangtze River[J].Journal of Yangte River Scientific Research Institute,2011,28(11):1-9.(in Chinese))
    [4]刘娟,舒行瑶,韩向东,等.镇扬和畅洲汊道二期整治工程[J].水利水电快报,2002,23(24):10-12.(LIU Juan,SHU Xing-yao,HAN Xiang-dong,et al.PhaseⅡRegulation Works at Hechangzhou Braided Channel in Z-Y Reach of Yangtze River[J].Express Water Resources&Hydropower Informaton,2002,23(24):10-12.(in Chinese))
    [5]吕宏兴,裴国霞,杨玲霞.水力学[M].北京:中国农业出版社,2002.(LV Hong-xing,PEI Guo-xia,YANG Ling-xia.Hydraulics[M].Beijing:China Agriculture Press,2002.(in Chinese))
    [6]钱宁,万兆惠.泥沙运动力学[M].北京:科学出版社,1991.(QIAN Ning,WANG Zhao-hui.Mechanics of Sediment Transport[M].Beijing:Science Press,1991.(in Chinese))