Scheduling modular projects on a bottleneck resource
- 作者:Kris Coolen (1)
Wenchao Wei (1) Fabrice Talla?Nobibon (1) (2) Roel Leus (1)
- 关键词:Scheduling ; Uncertainty ; Research and development ; Activity failures ; Modular precedence network
- 刊名:Journal of Scheduling
- 出版年:2014
- 出版时间:February 2014
- 年:2014
- 卷:17
- 期:1
- 页码:67-85
- 全文大小:901 KB
- 作者单位:Kris Coolen (1)
Wenchao Wei (1) Fabrice Talla?Nobibon (1) (2) Roel Leus (1)
1. ORSTAT, Faculty of Business and Economics, KU Leuven, Naamsestraat 69, 3000, Leuven, Belgium 2. QuantOM, HEC-Management School, University of Liège, Rue Louvrex 14, 4000, Liège, Belgium
- ISSN:1099-1425
文摘
In this paper, we model a research-and-development project as consisting of several modules, with each module containing one or more activities. We examine how to schedule the activities of such a project in order to maximize the expected profit when the activities have a probability of failure and when an activity’s failure can cause its module and thereby the overall project to fail. A module succeeds when at least one of its constituent activities is successfully executed. All activities are scheduled on a scarce resource that is modeled as a single machine. We describe various policy classes, establish the relations among them, develop exact algorithms to optimize over two different classes (one dynamic program and one branch-and-bound algorithm), and examine the computational performance of the algorithms on two randomly generated instance sets.
| |